IFN 0.00% 56.0¢ infigen energy

I noticed a comment on the Bodangora facebook page by a local...

  1. 483 Posts.
    lightbulb Created with Sketch. 36
    I noticed a comment on the Bodangora facebook page by a local saying they had noticed that 3 turbines were up which was dated 2 weeks ago. I estimate that is roughly three up in a week which puts the turbine erection progress about 15-20% along (the first unit was reported up on 17th April). Assuming no delays that would be 11 weeks to do all but given winter is approaching, that is more likely to be 13-15 weeks in my view. That put that stage at 17th - 31st July.

    Website lists earthworks/roadworks at 80%, substation construction  at 70% and commissioning at 5%.  Commissioning will lag erection so I would add probably a month to the last turbine date to get commissioning done. Let's say end of August is the conservative case.
    We should see some impact in the third quarter numbers released October if those assumptions are correct.
    Last edited by strangelogic: 15/05/18
 
watchlist Created with Sketch. Add IFN (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.