ANNOUNCEMENT TO ASX DRILLING REPORT: ARWON # 1 PEL 93, COOPER/EROMANGA BASIN, SA
Stuart Petroleum advises the well was drilled to 790 metres. The 9 5/8” surface casing was then run and cemented.
The rig is presently installing the bradenhead spool prior to installing the BOPs.
Drilling is expected to recommence Tuesday afternoon. The status of Arwon # 1 at 0600 hours (CST) on 27 September 2004 was: Location: PEL 93, 55km south-west of Moomba Planned Total Depth: 1930 metres
Current depth: 790 metres Operations: Preparing to install bradenhead spool Spud: 02.00hrs, 23 September 2004
Participants in the Arwon Joint Venture are: Stuart Petroleum Limited (Operator) 88.8% (STU) Cooper Energy NL 11.2% (COE)
Yours faithfully,
Tino Guglielmo Chief Executive Officer
STU Price at posting:
0.0¢ Sentiment: None Disclosure: Held