Revised Timeline:
EIS Lodgement - Progressive lodgement of EIS chapters September 2012
Formal EIS lodgement: 23rd November 2012
EIS Approval: 31 May 2013
JV Partner: Documentation complete by 31 March 2013
Finacial Investment Decision [FID]: 30 September 2013
Construction Start: 31 March 2014
First Steel Production: 31 March 2016