As you say Jukebox, that picture on the 20th does look like a truck has delivered something heavy into MIN's plant. Of course, it could have just been a heavy truck transporting something small..?
We are still waiting for the MIN update on commissioning, which was scheduled for midQ4, so we are already 3 weeks past the mid point of this estimate of 15 November.
You wouldn't think there would not be any significant delays in the construction of the MIN pilot plant. Any delays are likely to be during the commissioning phase, not the construction.
On top of this, the facility was erected before 3 November when Jukebox put up the first photo, and possibly the reactor deliver sometime between then and 20 November...
And from MINs AGM presentation on 22 November, "we are about to commission the pilot plant"
Surely it can't be too far away? I'm sure MIN are just as excited, so I'm sure there will be announcement even if Ward didn't think it was important.