Someone correct me if I'm wrong but after reading these excerpts...

  1. 2,178 Posts.
    lightbulb Created with Sketch. 27
    Someone correct me if I'm wrong but after reading these excerpts below from the release, it seems to me that CSE will never get funding. in the words of RSM Bird Cameron KZL stand to make $95.9m from mining the three deposits and stand to walk away with $50m after trucking costs of $40m.

    And they say that it will cost CSE $130m in development costs to mine the deposit. Seems to me CSE will make approx $30m loss if they go ahead, why would you borrow $130 to make $95m and in turn lose $30m.
    These figure are from Copper Strikes own targets statement, some of which i have pasted below.

    As part of the RSM Bird Cameron Corporate Pty Ltd independent assessment, independent engineers
    Mining One carried out a detailed evaluation of the entire Einasleigh Project. They estimated that the
    cash profit from mining the three high grade deposits in the Project would be $95.9 million at a copper
    price of US$3.30/lb, an A$ exchange rate of US$0.90, and a range of other assumptions. Using their
    estimated trucking costs for this region, Kagara would incur an estimated trucking cost of approximately
    $40 million (for 1.7 million tonnes of ore) for transporting the ore to their Mt Garnet processing plant. As
    a result Kagara would realise a net cash profit over the three year mine life of $56 million. This figure
    alone is almost FOUR times their current Offer.


    As at 30 September 2010, Copper Strike had $1.85 million in cash. The Mining One Pty Ltd Report which
    forms part of the Independent Expert Report contemplates a $130 million capital cost. The ability of
    Copper Strike to continue operations and finance development of the Einasleigh Project is dependent upon
    sufficient financing becoming available from debt, equity or finance markets in a timely and cost effective
    manner and at an appropriate price. Inability to finance in full or part a project or projects could result in
    reduced or no returns to shareholders. The ability to finance Copper Strike and/or specific projects can be
    impacted by events beyond the control of Copper Strike.
 