ARQ 0.00% 8.7¢ arq group limited

stokes testing delayed till end of wet

  1. 495 Posts.
    Further to the ASX release of 23 November 2007, ARC as the operator of the EP104/R1 Joint
    Venture, advises that it has suspended the testing of Stokes Bay-1 and removed all contractors
    and equipment from the site following recent rainfall.
    As was anticipated, the onset of seasonal rain has limited the safe access to the well, due to the
    low-lying terrain around the well site. The access track and well site have become temporarily
    unsuitable for the safe operation of heavy oilfield equipment.
    The timely testing of the Stokes Bay-1 well is a priority, and ARC Energy plans to recommence
    the Stokes Bay well testing programme as soon as safe access is available at the end of the
    wet season, anticipated to be around April 2008.
    The nature of the reservoir fluid and the source of pressure within the reservoir remain
    undetermined. Should the well be commercially productive better access facilities would be
    constructed to allow year round production.
    The next update on Stokes Bay-1 well will be issued when testing of the well recommences.
 