As far as I understand it, White Dam has around 3-4mths of production left until it exhausts the initial pit.
The rate of ton's placed on the leach pads, is around .75mt per quarter.
The Vertigo Depostit (currently 2.45mt)is awaiting Government approvals and when this comes on line, this will add another 9-10 months of production to the mine, which takes the life of mine to around mid year 2012 or so.
The next depostit to be proved up(7000m RC drilling was carried out last quarter), will be an extention to the Vertigo Deposit (if possible) and then White Dam North, with others after that, White Dam East & Rolling and Valley prospects (and other greenfields targets within a 3km radius of the current operation).
The last Quarterly also said further infill drilling was being undertaken in April this year at White Dam North.
cheers