    Exoil RI document released 06-11-2009 has the terms of the Songa Venus contract for Braveheart and Cornea, starting page 48
    Its a 6mb pdf at link below

    http://www.nsxa.com.au/ftp/news/021722150.PDF

    The pdf also contains some interesting info wrt Shell's previous drilling at Cornea

    Excerpt wrt Songa Venus contract details

    ""Songa Venus Rig and Drilling Service Arrangements with respect to WA-333-P
    On 14 July 2008, Exoil’s wholly-owned subsidiary Hawkestone Oil Pty Ltd (“Hawkestone”), acting in its
    capacity as Operator of the Browse Joint Venture, entered into two agreements relating to the steps taken to
    secure a rig to drill the Braveheart-1 well in WA-333-P.
    The first agreement, the Project Management Services Agreement, is between Hawkestone and Australian
    Drilling Associates Pty Ltd (“ADA”) and other parties pursuant to which Hawkestone has agreed to engage
    ADA to provide drilling management services to Hawkestone as operator. Hawkestone has agreed to pay to
    ADA aggregate management fees of $900,000 on behalf of the joint venture.
    The second agreement is the Drilling Co-operation Agreement between Hawkestone, ADA and all the other
    members of the consortium formed to contract the Songa Venus rig (“DCA”). Those consortium members
    are Hawkestone Oil Pty Ltd (ABN 23 052 812 236), Auralandia NL (ABN 53 004 913 884), Stuart Petroleum
    (Offshore) Pty Ltd (ABN 99 127 971 363), MEO Australia Limited (ABN 43 066 447 952), CNOOC Australia
    E&P Pty Ltd (ABN 85 118 934 062) and Anzon Energy Limited (ABN 43 097 972 364). Each of those
    consortium members is an Operator under the DCA and the italicised terms in this Section 1.9 are defined
    terms in the DCA.
    Under the DCA, the various consortium members have agreed how they will share certain rig costs, including
    mobilisation, demobilisation and towing costs and have agreed to pay various fees to ADA associated with
    ADA’s work in bringing the consortium together and securing shared services (logging contracts, work boats
    and the like).
    Each Operator agrees to undertake its Drilling Program in accordance with the DCA. Clause 3.9 of the DCA
    requires that each Operator acknowledges that it will be required under the Drilling Contract to pay the Drilling
    Contractor the applicable Daily Rate for each Day the Drilling Unit is utilised in undertaking that Operator’s
    Drilling Program.
    The DCA is based around each Operator having provided an estimate of the number of days that that
    Operator will require for its Drilling Program. In the event that any Operator’s Drilling Program results in what
    are defined as Shortfall Days, because that Operator’s Drilling Program was shorter in duration than
    estimated, that Operator is liable to pay the cost of those Shortfall Days. However, if ADA cannot recover the
    cost of those Shortfall Days from any Operator the DCA provides that all of the Operators have joint and
    several liability to pay the cost of the Shortfall Days to ADA.
    Under the terms of the DCA, ADA may require the Operators to provide ADA with any of:
    • a bank guarantee ;
    • a parent company guarantee ;
    • advanced payment of funds into an escrow account held by ADA.
    Although the DCA provides for specific liability for each Operator for other costs, including mobilisation and
    demobilisation costs, the DCA also provides for joint and several liability for those costs.
    The primary risk that each of the members of the consortium is exposed to under the DCA is a failure by any
    other Operator or Operators to meet their contracted drilling obligations and associated costs, thus leaving a
    shortfall in payment to ADA which, after the various enforcement procedures set out in the ADA are
    49
    exhausted in relation to the defaulting party, each consortium member must assume liability for. While each
    Operator has rights against a defaulting Operator to enable it to pursue recovery of any liability which it meets
    because of default, the recovery of such amounts might be uncertain and the prospect must exist that
    recovery might not be possible. However, the Company has no reason to believe that any of the Operators
    will default in any manner which will crystallise those joint and several liabilities.
    These agreements together form the contractual framework pursuant to which Hawkestone, as operator, has
    secured the Songa Venus rig to drill the Braveheart-1 well and the services of ADA to manage the drilling
    programme.
    1.10 Songa Venus Rig and Drilling Service arrangements with respect to WA-342-P
    On 21st October 2009 (with effect from 1st
    September 2009), Hawkestone, acting in its capacity as Operator
    of the Cornea Joint Venture, entered into an agreement with Auralandia N.L. (“Auralandia”) relating to
    securing a drilling slot on the Songa Venus to drill the Cornea 3 appraisal well in WA-342-P. Consequently
    the provisions of the Songa Venus Rig arrangements with respect to WA-333-P referred to in clause 1.9
    above apply with like effect to WA-342-P.
    Auralandia is a party to he Drilling Co-Operation Agreement referred to in clause 1.9 above and is an
    Operator under the DCA. Hawkestone has taken an assignment of all of Auralandia’s rights, obligations and
    interests in the Rig and Drilling Contract. This enables Hawkestone to utilise the Songa Venus rig to drill the
    Cornea 3 appraisal well.
    1.11 Songa Venus Drilling Contract and Deed of Accession
    By a combination of Deeds of Accession executed between Hawkestone Oil Pty Ltd and Auralandia N.L.,
    each of those parties acceded to the Songa Venus Drilling Contract (“the Drilling Contract”) and became a
    member of a drilling consortium comprising other parties who have acceded to the Drilling Contract. The
    Deeds of Accession are straightforward.
    The Drilling Contract is a contract entered into between Songa Offshore ASA (“Songa Offshore”) and
    Australian Drilling Associates Pty Ltd (ADA) under which the Songa Venus semi-submersible drilling rig
    (“Songa Venus”) has been contracted to drill combined programme for the drilling consortium.
    Under the Drilling Contract, Songa Offshore provides the Songa Venus to enable the drilling of wells for each
    of the members of the drilling consortium. The initial term of the Drilling Contract is for a period of 355 days of
    which 55 days are “move days”, and commenced on or about 8 January 2009.
    Songa Offshore has provided the rig at a daily operating rate of US$400,000 during the period in which the
    Songa Venus is operating and at a cost of US$388,000 during mobilisation, demobilisation and in relation to
    periods where the rig is moving. Under the Deeds of Accession, Hawkestone and Auralandia have effectively
    committed to pay for the Songa Venus rig for an aggregate of 36 days at the operating rate and 2 days at the
    moving rate. The allocation between the Braveheart-1 well and the Cornea 3 appraisal well is 15 days for the
    Braveheart-1 well and 21 days for the Cornea 3 appraisal well. The move days will be pro rated between the
    relative parties on that ratio.
    If all the wells, as contracted, are drilled in less than the Drilling Contract period (355 days) then each drilling
    consortium member in respect of whom there is a shortfall period (as defined) undertakes to pay Songa
    Venus the applicable daily rate for each day in the shortfall period. However, there is unlikely to be a shortfall
    period of material consequence, if at all, as the 355 days Drilling Contract period expires on or about 29
    December 2009.""
 