at 06:00 hours (WST) on Tuesday, 18 June 2013, the well was at a depth of 3660m MDRT
(measured depth below rotary table) and drilling ahead.
Operations over the last week have seen the cement plug drilled out and leak-off-testing of the 9?"
casing completed and drilling of the 8½" hole section commenced.
Planned operations over the coming week are to complete drilling of the 8½" hole through the zones
of interest.