No confusion, Prism don't have stage 2 FC. The final forestry clearance is required for the Prism Cement captive coal block. The stage 1 FC has been issued but the Stage 2 FC is still pending. The coal ministry states that the ML will be issued within a month of forest clearance. No FC, no ML.
Remarks on progress:?] Explored. GR obtained, BG submitted. UG mine. FC (Stage?]II), EMP, ML & LA are pending. Stage?]I clearance for FC obtained. Grant of ML is pending for FC. Stage?]II FC is expected by Aug. 10. ML within a month of forest clearance.