So numbers, We borrow $140 mill @ 20%, if constructed in 18...

  1. 592 Posts.
    So numbers,

    We borrow $140 mill @ 20%, if constructed in 18 months we then owe more than $42million extra at first gold pour. If this is delayed to 24 months....at least $56 million. (these interest amounts weren't compounded).

    The market will discount us big time according to all the risk involved in repaying the debt.

    The net cash surplus given by atv in many of its announcements DOES NOT take into account any incurred interest.

    POG @ $1700/oz gives cash surplus of $337 million. Lets say 42 million interest from construction, $180 debt now. The mine will net $92mill/year, take around 2yrs 4 months to pay back whilst incurring an additional $40mill debt.

    So when taking debt into account the cash surplus goes from $337mill to $337-$82 = $250 mill, and the payback went from 18months to 28 months.... OUCH

    cash surplus has decreases by 25% and repayment period has increased substantially. Therefore the NPV given by atv needs to be decreased by more than 30%.... OUCH

    from $206mill to $140mill.....

    The market WILL discount according to risk of payback time due to construction/mining/processing risk. I have NOT included any of the risks....
 
watchlist Created with Sketch. Add ATV (ASX) to my watchlist
(20min delay)
Last
1.8¢
Change
0.001(5.88%)
Mkt cap ! $14.13M
Open High Low Value Volume
1.6¢ 1.8¢ 1.6¢ $5.501K 312.5K

Buyers (Bids)

No. Vol. Price($)
4 935750 1.7¢
 

Sellers (Offers)

Price($) Vol. No.
1.8¢ 549999 4
Last trade - 16.10pm 28/11/2024 (20 minute delay) ?
ATV (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.