By the 19th May, the 3 hole diamond drilling program had commenced and is
expected to take about 10 days to complete, then 4 or 5 days to log the cores
prior to despatch to the lab for testing.So 15 days? after drilling commenced
by the 19th May, guessing the samples have been logged and as of today, 1st June are possibly heading for the lab.19/5/16 P2
Assuming no delays and all my other guesstimates are correct, results of
drilling in the red hot high grade zone at Diabarou could be due
from Thurs 9th June onwards.
Apart from giving our SP a great chance of a lift with high grade gold results
expected (by me), the DD results will provide valuable structural information to
assist in the design of the RC program (18 holes for 2,400 metres).
The DD results will guide the RC drilling campaign to test the open pit resource
potential of this prospect.
While the DD cores are being logged about now, the rig is headed for a quick trip to Selingouma to commence a planned 8,000 metre aircore (AC)
drilling program before returning to Diabarou to undertake the RC drilling program,
which consists of (18 holes for 2,400 metres).Selingouma is in the bottom section
of the Dandakoproject lease and Diaborou is at the North end.
All fully funded, heaps of drilling, heaps of testing results and looking really
good for the SP in the next few months.
Just the opinions of a Doodledog DYOR