Sept 13 (Reuters) - Newcrest Mining Ltd (NCM)
- Cadia east panel cave 1 production recommences
- Expected that Cadia east production rates will have been fully restored to normal by end of March 2018
- Newcrest completed 'test and response' phase of panel cave 2 (pc2) on 19 July 2017, with ramp-up in production from pc2 continuing
- Remediation and upgrade work required to recommence use of cadia east's panel cave 1 (pc1) crusher chamber has been completed
- Remediation and upgrade work continues on other areas in pc1 extraction level, which is expected to be completed by end of dec 2017
- Prohibition notice has been amended to allow operations to recommence as areas are upgraded in accordance with submitted plans