MRX 0.00% 0.7¢ matrix metals limited

mining commences at leichhardt buy

  1. 19,620 Posts.
    lightbulb Created with Sketch. 35
    1131 Hay Street, West Perth, W.A. 6005 PO Box 1036 West Perth, W.A. 6872
    Tel: (08) 9486 7100 Fax: (08) 9486 7300. Website: www.matrixmetals.com.au Email: [email protected]
    23 April 2007
    Manager Company Announcements
    Company Announcements Office
    Australian Stock Exchange Limited
    Level 10, 20 Bond Street
    ABN 42 082 593 235
    SYDNEY NSW 2000
    Electronic delivery
    No of pages: 2
    Mining Commences at Leichhardt
    Summary
    • Mining operations have commenced at Mt Watson
    • Mt Watson haul road construction will be completed during April
    • Ore haulage to the Mt Cuthbert processing plant will commence during May
    • Leichhardt processing plant refurbishment will be completed during May
    • Commissioning of crushing operations will commence during June
    • First copper cathode production will be during July 2007
    Leichhardt
    Leichhardt will produce copper cathode at the Mt Cuthbert processing plant using ore
    from the nearby Mt Watson orebody, utilising the heap-leach - solvent extraction -
    electrowinning process (“SX/EW”).
    The mining fleet of one Komatsu PC 850 excavator (85 tonne capacity), one Komatsu
    PC220 excavator, three Komatsu 465 dump trucks (50 tonne capacity each), one
    Komatsu 275 bulldozer, one Komatsu 65S grader, one water cart and the drill and blast
    rig are on site and mining operations have commenced. Initially, top soil will be
    removed and stored for later use and then stockpiles of ore will be built up at the Mt
    Watson mine site.
    Construction of the haul road from the Mt Watson orebody to the Mt Cuthbert
    processing plant has essentially been completed and it is anticipated that the haul road
    will be fully operational by the end of April. Ore cartage will commence during May,
    with stockpiles of ore to be built up at the Mt Cuthbert ROM pad.
    The crushing circuit will arrive on site during May and its commissioning will be
    undertaken during June. During this commissioning stage, new ore will be stacked on 2
    the leach pads which will enable the irrigation of ore during June. The crushing
    circuit has been built to accommodate the expanded Stage 2 production requirements of
    10,000 tpa of copper cathode, further details of which are below.
    The final stages of refurbishment of the Mt Cuthbert processing plant are currently
    being undertaken. This work has included replacement of the old electrowinning cells
    with “as-new” cells previously purchased for the project, refurbishment of the solvent
    extraction tanks, overhaul and repair of the process water ponds and the installation of a
    new acid delivery system to the agglomerator. Also, a new additional accommodation
    village and facilities are being installed. A engineering contractor is managing these
    activities and their construction team is expected to demobilise during the second week
    of May.
    A specialist mechanical and electrical commissioning team from the same engineering
    contractor is scheduled to arrive at Mt Cuthbert during May to complete all of the
    inspection test plans prior to practical completion. A separate specialist process
    commissioning team will mobilise to site in early May to ensure effective
    commissioning of the entire processing circuit.
    Planned Production Expansion
    Stage One production from Leichhardt will produce copper cathode at a rate of 5,500
    tpa of copper cathode, by treating of 2.1 million tonnes of ore over a four year period
    from the Mt Watson orebody.
    The Mt Watson orebody has a total resource of 8 million tonnes of ore. Following
    further metallurgical and geotechnical testing, life extensions and/or a production rate
    increase is planned for the Mt Cuthbert processing plant. In addition, there are
    previously identified prospects at Mt Earl, Mt Wonder, Tewinga and Boomerang (all
    within the vicinity of Mt Watson) which may also provide the opportunity for further
    extensions and/or production rate increases.
    The Mt Cuthbert plant can quite quickly be upgraded to a capacity of 10,000 tpa of
    copper cathode production. Matrix has already purchased the main equipment
    expansion components required for the upgrade, being the rectifier and electrowinning
    circuit. The upgrade of the Mt Cuthbert plant to 10,000 tpa of copper cathode
    production was previously the subject of a study by Matrix. Once results of the
    metallurgical testing and geotechnical drilling are available the study will be updated
    and economics assessed.
    Yours Faithfully
    Shane McBride
    Managing Director
 
watchlist Created with Sketch. Add MRX (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.