IDO 0.00% 0.3¢ indo mines limited

FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST...

  1. 17,783 Posts.
    lightbulb Created with Sketch. 103
    FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH
    MARGINS.

    Feasibility Study completed on a 2 million tonne per annum iron sand mine for the Jogjakarta Iron Project.

    ? Strong projected cash margins and low capital cost per annual tonne of production
    ? US$24.20 per tonne operating cost (FOB) for 55% Fe concentrate
    ? US$158.3 million capital cost
    ? Project IRR 44.5% (before tax)
    ? 163.5 million tonnes Probable Mining Reserve (surface sands) @ 13.7% Fe
    ? Final Project approvals well advanced
    ? Mining operations targeted to commence within 18 months.

    At spot iron ore pricing and foreign exchange rates, the Project has an IRR of 83.1% (before tax).
 