So lets revisit the PFS calcs which they came out with in August 07.
Quote...
The Project capital and operating costs, based upon the current investigations to date are:
–Capital Cost
Stage 1 (0.5mtpa) A$437.3M
Stage 2 (1.0mtpa) A$302.5M
–Operating Cost
0.5mtpa A$270.65/t MPI
1.0mtpa A$252.15/t MPI
–EBITDA per tonne
0.5mtpa A$151.43/t MPI
1.0mtpa A$169.93/t MPI
–Merchant Pig Iron Forecast Price A$422.08/t
...now we replace MPI of $422 with $800 (using AUD 0.9) and get...
–EBITDA per tonne
0.5mtpa A$530/t MPI
1.0mtpa A$548/t MPI
Now would this be right?
0.5mtpa * $530 = $265m EBITDA
1.0mtpa * $548 = $548m EBITDA
Probably project costs have gone up a bit too, energy for one. But still sitting on a gold mine by the looks.
-