Announcment from Superloop on Indigo, which will compete with ASC, i thought they where about 5 months behind, but despite their words about completing segments early, it looks like they have a lot more to do and are behind schedule. Looks like it wont compete with ASC until mid-2019, which is good for us.
It currently states RFS in Q1 2019 on the project website, so that looks like a delay of a couple of months.
https://subpartners.net/indigo.html
"Installation of the INDIGO Central cable is due to complete early December and once in service, it will providea new and unique subsea communications link between Sydney and Perth.This announcement follows the recent landing of the INDIGO WEST cable from Singapore to Perth and thecommencement of INDIGO Central marine installation from Perth, both announced in September.
...
Construction of the overall INDIGO cable system is on-track and will be ready for service by mid-2019."
https://hotcopper.com.au/threads/ann-indigo-cable-system-lands-in-sydney.4510683/