HIGHLIGHTS FROM THE QUARTERLY REPORT 31 DECEMBER 2006
• Millsell CWP commissioned and planned tonnages of +7,000 tons of saleable tonnage by the end of January 2007 were achieved.
• Construction of PRP plants at Millsell and Steelport bought forward with completion scheduled for the end of May 2007, which is well ahead of previous planned construction in 2008.
• Everest North drilling progresses well
• Chrome Tailings Re-treatment Project ("CTRP") produced 1866 PGM ounces for the December 2006 quarter, Sylvania attributable: 466 PGM Ounces