Agree with Masterfoods on this one. Yes there are more than likely rigs in the vacinity. However, one on standby (sitting waiting) would be a costly exercise.
Don't want to put your fire out but if you think the well will be on production 15 days after approval is granted you're dreaming. It won't happen.
Approval will be granted and the rig contracted to suit the operators schedule. Once on the well pad the existing well will be drilled out and 15 days later (IF the crew has no down hole issues) it will be put on production eg. Wellhead installed and flared.
Then over a period of 12 months, testing will be carried out to ascertain flow rates and sustainability.
Hopefully we will get periodic updates..........?
Gaspew ;)
- Forums
- ASX - By Stock
- gas discovery booked 3p reserves of 114 pj
CnG,Agree with Masterfoods on this one. Yes there are more than...
-
- There are more pages in this discussion • 131 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Add ROG (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.8¢ |
Change
0.000(0.00%) |
Mkt cap ! $32.53M |
Open | High | Low | Value | Volume |
0.8¢ | 0.8¢ | 0.8¢ | $182.1K | 22.77M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
25 | 36939618 | 0.7¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.8¢ | 11435752 | 15 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
20 | 23393673 | 0.002 |
28 | 92682599 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 989929 | 2 |
0.004 | 39011968 | 15 |
0.005 | 19447740 | 8 |
0.006 | 8100000 | 4 |
0.007 | 6550000 | 3 |
Last trade - 16.10pm 08/11/2024 (20 minute delay) ? |
ROG (ASX) Chart |