this out of petroleum news... could be a good move to get involved in this project as EGO has power plants in this project (ERM i believe).
Empire details Perth Basin gas plant
Friday, 22 October 2010
EMPIRE Oil & Gas is making plans for a processing plant at EP 389, Perth Basin, capable of processing more than 10 million cubic feet of gas and 500 barrels of condensate per day.
The plant, which is being designed by Momentum Engineering and likely to be built locally, will process gas from the Gingin West-1 discovery and possibly the Red Gully-1 deviated well if it is successful.
Empire noted the site for the plant had not been settled on as there were other structures along the 60-kilometre long Gingin to Bullsbrook Trend that were potentially gas and condensate charged.
It added additional finds could either maintain or increase the production rate and that provision for additional pipeline to the gas plant location is also in the planning.
KEY Price at posting:
4.5¢ Sentiment: LT Buy Disclosure: Held