Tried to go back to previous ANN regarding Casing at 14000 ft, but unable to find.Sure Co advised that this would be happening.
As previous threads have stated Casing is used to prevent a blowout in the well and used at levels where high PSI Gas is either found or expected. With the hole depth and the amount of Casing being installed it is a slow and precise operation and can day 3-5 days.
ANN at 13800 ft on or about 11 March so assume 14000 ft on or about 12 March then 5 days start drilling 18 March if use 300 ft day then 6-7 days to TD. My guess for what it is worth is 24-25 March which will be a huge gamble for our QPNO friends.
Hole logging could then take a few weeks but the way this hole is being prepared would should have HC shows this week.IMHO