    Hi Tonio,

    The reason I didn't add it is that different grades of the alluvium will require very different ratios of the 'wet processed' ore produced.

    For example:

    400 tonnes Alluvium (grade of 0.03%) is required to produce one (1) Tonne of wet processed ore with grade of 12%.

    While 160 tonnes Alluvium (grade of 0.05%) is required to produce one (1) Tonne of wet processed ore with grade of 8%.

    For the former it is 45,000 tonnes, while for the latter it is closer to the 120,000 tonnes being 112,500 Tonnes.

    With such a difference in volumes I have assumed the ROM is the amount of material required at the begining of each process.

    Cheers,

    Stoops.


 