May I suggest that you not put the same volume of material through the dry processing as the wet processing plants?
Therefore, should you add both the wet and dry processing costs multiplied by 18MTPA?
In my opinion because of the large grade increase by wet processing you need to
work out the material that will be processed for each stage.
Therefore, 18MTPA of Alluvium will create 45,000 Tonnes of ore to be dry processed.
That is the amount, 45,000 Tonnes, you multiply by $0.45 not 18Million.
Try that and see how you go.