The little map Page 2 from your link shows an 800 km transmission line route between the projects. There isn't much mileage from $150m. Its about 12% of what is needed.
Must read these things carefully -
"The government will invest a further $100 million to help
fund a 50 megawatt hydro-electric power station at the (Burdekin Falls)
dam, subject to completion of the business case."
"The Queensland Government will commit $150 million to
develop strategic transmission infrastructure in North
and North-west Queensland to support a clean energy
hub, subject to a feasibility study."
The map from Powerlink shows the 185 km of 275 kV transmission line that is needed just for Genex and the $150m only pays for half of it. Does that mean all the other renewable projects shown on Page 2 are out in the cold already?
Anyway, probably all stitched up long ago.