BT when they start production has no value. It is when they finish that counts.
From the last quarterly.
Design drawings for the roaster modifications are now complete and are being finalised as construction drawings. These will be sent to selected fabricators for quotes later this week.
It is anticipated that commissioning of the EVAP unit will commence in June
Now from this quarterly.
The refractory-lined roaster cap and off-gas ductwork which will be integrated with the EVAP gas scrubbing system are in the design phase.
So my reading is that in the 3 months they have gone backwards. Timelines and budget are out the window. So who knows if or when this version of the plant be finished.
On a positive, they have worked how to email this report and not fax it.