Actually I just read this...
"The construction of the Service Shaft, originally planned from surface to Level 8, and due for completion in September 2016 is now scheduled to be completed in June 2017 as a result of the decision to deepen the shaft to Level 10 (Figure 2)."
Whilst probably advantageous for the long term, that's not ideal for improving operations in the short term.