Making progress, good to see the by-pass will be completed next month. Report below:
During October
Re-commissioning of Plomosas continued above the Level 5 production haulage drive with increased development and stope mining from the 1000 stope. The focus is on opening up more stope work areas to access ore.
Haulage trucks and load haul dump loaders continue to be mobilised as more headings become available to support the equipment within the mine. Equipment availability and utilisation were below expectations as the contractor established support services and systems at Plomosas.
Stope production was restricted due to maintenance issues causing limitations on decline haulage and transfer of the ore from stopes to the loading pocket. The decline bypass advanced 48m during the month and is now 70% complete.
The bypass is expected to be completed during November. This will remove the bottleneck for the transport of ore to surface, allowing for increased ore haulage with larger, faster trucks that are being mobilised to site.
- Forums
- ASX - By Stock
- Ann: Plomosas Mine Production Report October 2018
Making progress, good to see the by-pass will be completed next...
-
-
- There are more pages in this discussion • 37 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add CZL (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
ACW
ACTINOGEN MEDICAL LIMITED
Andy Udell, CCO
Andy Udell
CCO
SPONSORED BY The Market Online