A decision has therefore been made to replace Rig-1 with Rig-2 to complete the Malolos-1 workover and flow testing. Rig-1 is a larger rig with better capacity to complete the workover and it will also be worked 24 hours/day whereas Rig-1 is only working 12 hours/day. Rig-2 will retrieve the 5 inch casing and then mill out the junk with a larger 6 inch bit. The oil bearing sandstones will then be perforated and tested. Whilst there will be a delay of about a month while the two rigs are changed out this action will make the workover operation simpler to complete.