    There is more to come from Eliwana. As ellimb suggests, this Announcement may cover the same work as the 31/12/2018I Announcement,  except the value has increased marginally, and a formal contract has now been executed. The original Announcement stated:

    NRW Preferred Contractor for Fortescue’s Eliwana Rail Project Stage 1

    NRW is pleased to announce it has been selected by Fortescue Metals Group Ltd (Fortescue) (ASX:FMG) as the preferred Contractor to deliver the Stage 1 Earthworks, Roadworks and Drainage Works of Fortescue’s Eliwana Rail Project.

    Fortescue and NRW will move to finalise outstanding matters prior to formal contract execution.

    The project value is circa $57m. NRW will utilise its existing civil construction fleet for the project.


    As I then wrote in respect to the following list:

    Work packages 2, 3, 5 and 20 have either been awarded (e.g., package 3), or they may be potential wins for NWH.
    1. Transformers .. 24/08/18–07/01/19
    2. Bulk Earthworks for Processing Plant and Non-Process Infrastructure
      ..... 23/10/18–01/02/19 Target Award 03/19
    3. Eliwana Bulk Earthworks and Roads .. 21/08/18–31/08/18 Target 3/10/18
    4. Rail Camp 50 and 95 .. 24/08/18–14/09/18
    5. Bridge Contractor .. 24/08/18–17/09/18 Target Award 5/1/19
    6. Bridge Girder Supply .. 24/08/18 – 17/09/18
    7. Supply of Sampling Equipment .. 24/08/18 – 20/09/18
    8. Apron Feeder .. 23/08/18 – 21/09/18
    9. Railway Ballast Supply and Delivery .. 21/08/18 – 10/09/18
    10. Potable water treatment Plant .. 23/08/18 – 12/10/18
    11. Construction Communications .. 18/09/18 – 19/10/18
    12. Rail Communications .. 18/09/18 – 19/10/18
    13. Eliwana Early Mining Fleet Maintenance and NPI .. 28/09/18–26/10/18
    14. Conveyor Drives .. 17/10/18 – 27/10/18
    15. Earthworks Eliwana rail - 20 to 143km .. 18/09/18–31/10/18 Target 4/19
    16. Tramp Metal Magnets .. 26/10/18 – 05/11/18
    17. Low Voltage Switchrooms .. 16/10/18 – 08/11/18
    18. High Voltage Switchrooms .. 16/10/18 – 09/11/18
    19. Grade Control Reverse Circulation Drilling .. 23/10/18 – 20/11/18
    20. Primary Crushing and Ore Processing Facility .. 30/10/18 – 22/11/18
      Target Award 20/3/19
    21. Diesel Power Generation .. 06/11/18 – 23/11/18
    22. Stockyard and Overland Conveyor Construction .. 18/10/18 – 23/11/18
    23. Train Loadout Facility and Train Loadout Conveyor Construction
      .. 18/10/18 – 23/11/18
    24. Low Voltage Variable Speed Drives .. 31/10/18 – 26/11/18
    Last edited by Pioupiou: 15/02/19
 
watchlist Created with Sketch. Add NWH (ASX) to my watchlist
(20min delay)
Last
$3.95
Change
0.030(0.77%)
Mkt cap ! $1.574B
Open High Low Value Volume
$3.97 $3.98 $3.92 $2.104M 533.0K

Buyers (Bids)

No. Vol. Price($)
5 14160 $3.93
 

Sellers (Offers)

Price($) Vol. No.
$3.95 10387 3
View Market Depth
Last trade - 16.10pm 22/11/2024 (20 minute delay) ?
NWH (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.