Details MPW works approved for the Ear Grey project:
2. Details of the proposed work (a) Deconstruction and removal of historic Mt Holland structures, plant, equipment,debris and waste materials (historical infrastructure), to remove environmentaland safety hazards and ensure a safe site for future employees and contractors.
(b) Construction of new groundwater bores for construction purposes and dustsuppression.
(c) Construction of new infrastructure and upgrade of existing infrastructure requiredto carry out the preliminary works including construction of a 60-person accommodation camp (including waste watertreatment plant (WWTP and sprayfield), landfill, temporary concrete batchingplant and water supply infrastructure),o construction of site offices, storage and laydown areas,o upgrade of the existing power supply and communication infrastructure,o maintenance of existing roads.
(d) Storage of long lead infrastructure components required for the mining proposalwithin existing disturbed areas.