so
77 is now part of the workover programme
73's production has dropped from 52 to 26 and now is down to around 20 boed
73 is also now shut-in as part of a pressure test
78 spudding more than likely delayed till Q1 2016
and bhandut, having been due to be completed by mid Nov is now planned to be prior to end of Dec