29th April - drilling commences
27th June - drilling of Columbus #1 commenced (the 2nd well in 3 well program)
28th July - all 3 wells successfully completed upper vertical sections
14th Sep - rig mobilization to Columbus drill site completed for drilling deviated section of final well.
26th Sep - final drilling of Columbus to start this week
4th Oct - final drilling of Columbus started .... finally (I guess)
It is 5 full months since the drilling of these SHALLOW Pierre wells which do not require hydraulic fracturing to complete and still not completed. Lucky (?) these are not deep wells requiring fracturing - might set a new drilling record.
There is always a reason why things happen the way they do. This just seems an inordinate amount of time given timings of "peers".
Soon see the fruits of their labors.
Good luck