From qtry report;
Pre-production and rehabilitation work in October and November were on plan, however the production ramp up in
December was slower than forecast due to a combination of factors, including:
• Delays in recruiting various operational and maintenance roles;
• Mobile equipment availability; and
• A severe storm which required personnel to be deployed elsewhere to repair damage and to reinstate services.
So we knew there had been issues, but this was nearly 2 months ago. Bit smelly. Bank wants a bigger piece of it