Yep, all positive.
Essential to have assurance on water, of course, and a big tick there as you say Coalboy. And the ongoing met testwork plainly presenting useful insights:
The 2019 results indicate that at both Helens and Lewis overall recovery (either at 24 hour or 48 hour leach times) and Tails Grade is relatively insensitive to P80 Grind Size up to 150um. There appears, at least in the Master Composites at Helens and Lewis, to be significant scope for running the proposed plant at a significantly coarser grind than the 75um grind chosen in the 2017 DFS plant design. A significantly coarser grind requirement implies either lower power demand or increased throughput, or a combination of the two, to provide optimal results.