    I don't expect work will start for a while even once approval for the plant expansion is given. It takes a while to procure the equipment and materials and then to ship them all to Songo Songo Island.

    I'm no engineer so I'm not sure on the specifics but as I understand it the tie in can easily be achieved separate from the expansion however it is immensely cheaper to do it as part of the expansion.

    I am curious with the process of the expansion in terms of when the tie in can be done and be operational. At, or near, the start? Somewhere in the middle? Or would we have to wait until the expansion is fully complete?

    Regardless of timing of the expansion, what we need before ANY capital raising is approval for expansion of the plant and drilling in the UK to at least be under way to boost the share price so that any raising is not too dilutionary.
 
watchlist Created with Sketch. Add KEY (ASX) to my watchlist
(20min delay)
Last
0.1¢
Change
0.000(0.00%)
Mkt cap ! $2.262M
Open High Low Value Volume
0.0¢ 0.0¢ 0.0¢ $0 0
KEY (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.