    Final Operating Approval
    Received
    Matrix Metals Limited ("Matrix") is pleased to announce that the final statutory
    approval required for the commencement of production at the Leichhardt
    Operation was received from the Queensland Environmental Protection Agency
    yesterday, 6 December 2006.
    The approval relates to an amendment to the Mt Cuthbert Plan of Operation
    allowing the Mt Cuthbert plant and infrastructure to move from a care and
    maintenance status to operating status.
    Along with the approved Plan of Operations for the development of the Mt
    Watson mine and the Environmental Authorities related to both Plans of
    Operations, all approvals are now in place for the commencement of operations
    at the Leichhardt Operation.
    Pre-Production Activities at the Leichhardt Operation Continue
    Work activities related to the commencement of copper production from the
    Leichhardt Operation continue and include the following:
    • Refurbishment of the Mt Cuthbert SX/EW plant and associated
    infrastructure.
    • An order has been placed (value of $1.2m) for stage one of the Village
    upgrade and sewage system with delivery of stage one to site due in
    early January 2007.
    • Mobilisation is scheduled within the next few weeks for a contractor to
    commence various earthworks projects including the upgrade to the
    2
    access road, reinstatement of the Leichhardt River crossing, a program
    of work in the leach pad area and general works in the Village area.
    • The tender document for the combined mining, ore haulage and crushing
    and stacking contract is scheduled to be issued later today.
 