    Linked is AGC's latest (January 2017) presentation. Interesting is their timeline, the milestones of which of course are subject to AGC being able to raise the required capital - as with most company timelines.

    Milestone Duration

    N.I. 43-101 Feasibility Study on the Coosa Graphite Project includes Detailed Engineering ~ 10 to 12 months from commencement

    Pilot Plant 2 (Secondary Processing to produce CSPG) in conjunction with the Feasibility Study ~ 10 months from commencement

    Battery Material Development: CSPG Production and Test Work ongoing

    Marketing CSPG Samples to Potential Offtake Partners ongoing

    Alabama State Environmental/Mine Permitting ~ 9 to 10 months from commencement

    Project Construction/Build Out Open-Pit Mine, Primary and Secondary Processing Plants < 6 months

    Commercial Production Q2 2018

    http://alabamagraphite.com/wp-content/uploads/corporatePresentationMaster-2017-01-13-web.pdf
 