the quarterly already indicated the long lead items, just not the EPC contract..
Stage 2 Plant Upgrade – Fines Circuit
• Work continuing to schedule with commissioning of Fines Circuit expected to commence during the September 2019 Quarter. • Detailed design progressing, ordering of long lead items commenced.
• Targeting increased combined throughput to 300tph and recovery of 72-80%