BGD 7.14% 26.0¢ barton gold holdings limited

On their steel plant public consultation invitation it's $4...

  1. 1,720 Posts.

    On their steel plant public consultation invitation it's $4 billion,
    http://www.gladstonesteelproject.com.au/pdf/Boulder%20Steel%20Community%20Consult.pdf

    On Queensland Government site it's $2.8 billion,
    http://www.dlgp.qld.gov.au/projects/mining-and-mineral-processing/steel/gladstone-steel-making-facility.html

    On Boulder Steel project home page it's $1.8 billion,
    http://www.gladstonesteelproject.com.au/index.html

    A big difference, I phoned Carl Moser to shed a little light on the quoted variations this afternoon,

    $1.8 billion is the 1st stage
    $2.8 billion is the plant cost
    $4.0 billion is the total cost including infrastructure
 
watchlist Created with Sketch. Add BGD (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.