Reasons why the DNRM will fast-track the ML once the Native Title agreement is finalised:
* No objections were received when lodged.
* DNRM has accepted the Facility Description.
https://www.dnrm.qld.gov.au/__data/assets/pdf_file/0006/305466/qld-guidance-note-23.pdf
* Compensation agreements with landholders are finalised.
* Environmental Authority (EPSL03068015) has been granted.
* The Environmental Bond (financial assurance) is expected to reflect the small area of disturbance and the limited activities on site – ore processing and tailings disposal will be off lease.
* Mine planning for phase 1 is complete - very simple near surface orebody.