Minara Resources Ltd (ASX:MRE) has revealed that output at its Murrin Murrin project is still on standby, following a technical failure last week.
The nickel producer says the project’s acid plant, where acid goes through ore to recover a nickel solution, remains offline.
The failed heat exchanger unit now requires a replacement and is being sourced.
Minara says the impact on the company’s 2011 production guidance, of up to 37,000 tonnes of annual nickel production, is being assessed.
Minara Resources generated a net profit of $58.3 million in the 2010 calendar year.