AQA 0.00% $3.37 aquila resources limited

quarterly

  1. sam
    412 Posts.
    AQA Quarterly Report ? December 2010 1
    Quarterly Report
    December 2010
    Aquila
    Aquila Resources Limited Telephone: +61 8 9423 0111
    Facsimile: +61 8 9423 0133
    Level 2, Aquila Centre
    1 Preston Street, Email: [email protected]
    Como WA 6152 Website: www.aquilaresources.com.au
    Anketell Point with Dixon Island in the foreground
    HIGHLIGHTS
    AQA Quarterly Report ? December 2010 2
    COAL
    Isaac Plains Coal Mine
     There were no Lost Time Injuries (LTIs) during
    the Quarter with the 12 month rolling average
    LTI Frequency Rate for the Isaac Plains Coal
    Mine being maintained at zero LTIs per million
    man hours worked.
     The mining operation at Isaac Plains was
    severely affected by weather in December which
    resulted in below budget overburden movement
    and coal production.
     A total of 390Kt of saleable coal was produced
    during the Quarter.
     Coal sales for the Quarter were 625Kt.
     Dragline erection continues on schedule and is
    expected to be completed and operational
    during the June Quarter 2011.
    Eagle Downs Hard Coking Coal Project
     The Definitive Feasibility Study work programme
    advanced during the Quarter.
     Evaluation is underway on the tenders for
    surface, CHPP and underground work
    packages.
    Washpool Hard Coking Coal Project
     Work continued on the Definitive Feasibility
    Study process which is expected to be
    completed by September Quarter 2011.
     The draft EIS has been submitted to DERM for
    review.
    Talwood Coking Coal Project
     The exploration programme was completed
    during the Quarter.
     An updated Resource Statement was released
    during the Quarter increasing the total Resource
    to 246Mt of Indicated and Inferred Resource.
    IRON ORE
    West Pilbara Iron Ore Project
     An updated JORC Resource for the West
    Pilbara Iron Ore Project was reported and now
    totals 927Mt at 57.5% Fe, which is an increase
    of 37% over the previous Resource Statement.
    Approximately 87% of the Stage 1 development
    Resource (687Mt) is now in the Measured and
    Indicated categories.
     Following the completion of mining studies, a
    maiden JORC Ore Reserve of 445Mt at 57.1%
    Fe was reported for the Stage 1 development
    area. The overburden to ore ratio reduced to
    1.13 from 1.85 previously.
     The Anketell Point Port Public Environmental
    Review (PER) was released for public comment
    on 20 December 2010.
     The Office of the Environmental Protection
    Authority (OEPA) commenced assessment of
    the Mine and Rail PER following the public
    review process.
     An additional four Memoranda of Understanding
    were executed, taking the total to 38 MoU with
    steel mills in China, Japan, Korea and Taiwan.
     Conditional approval was granted by the API
    Joint Venture Participants to undertake mine
    development for Stage 1 of the West Pilbara
    Iron Ore Project.
     The RC drilling programme continued at the
    Weckl prospect. Drilling highlights include
    (Detrital intercepts >20m):
     24m @ 57.65% Fe from 16m in WKRC092;
     20m @ 56.21% Fe from 16m in WKRC140;
     20m @ 55.83% Fe from 18m in WKRC141;
     24m @ 57.13% Fe from 6m in WKRC206;
     22m @ 58.18% Fe from 6m in WKRC214;
     30m @ 56.71% Fe from 16m in WKRC218;
     22m @ 56.81% Fe from 8m in WKRC270.
    All intercepts were calculated for greater than 52% Fe cut.
     An RC drilling programme was completed at the
    Downey prospect. Drilling highlights include
    (Detrital and channel iron intercepts >15m):
     18m @ 54.88% Fe from 10m in DORC016;
     18m @ 56.40% Fe from 18m in DORC031;
     30m @ 54.29% Fe from 4m in DORC053.
    All intercepts were calculated for greater than 52% Fe cut.
     An initial round of RC drilling was completed at
    the Buckland Hills prospect resulting in
    extensive channel iron mineralisation being
    identified. Assay results are pending.
     An infill RC drilling programme has continued at
    the Hardey deposit with highlights including
    (Bedded iron intercepts >80m):
     90 m @ 59.58% Fe from 0m in HARC287;
     138m @ 63.12% Fe from 0m in HARC329;
     128m @ 60.89% Fe from 0m in HARC351;
     84m @ 62.54% Fe from 64m in HARC356;
     106m @ 62.58% Fe from 10m in HARC361;
     108m @ 62.31% Fe from 26m in HARC366.
    All intercepts were calculated for greater than 58% Fe cut.
    HIGHLIGHTS
    AQA Quarterly Report ? December 2010 3
    Thabazimbi Iron Ore Project
     An updated JORC Resource at Meletse Iron Ore
    Deposit was reported and now totals 47.6Mt at
    62.9% Fe, which is an increase of 117% over
    the previous Resource Statement.
    Approximately 33% of the Resource is now in
    the Indicated category.
     Drilling continued at the Meletse Iron Ore
    Deposit where the Deposit remains open along
    strike and at depth. Significant high-grade Fe
    intercepts received during the Quarter include:
     4m at 61.56% Fe from 254m and
    3m at 62.06% Fe from 288m in DT38;
     14m at 64.55% Fe from 200m in DT40;
     3m at 60.22% Fe from 306m in DT55;
     4m at 60.45% Fe from 148m and
    8m at 60.02% Fe from 159m and
    23m at 66.14% Fe from 182m and
    11m at 61.22% Fe from 246m in DT50;
     27m at 62.83% Fe from 248m in DT53;
     33m at 65.75% Fe from 210m in DT60;
     6m at 62.36% Fe from 182m and
    7m at 62.31% Fe from 202m and
    31m at 67.49% Fe from 230m in DT62;
     13m at 65.43% Fe from 232m in DT56;
     5m at 61.43% Fe from 245m in DT53.
    All intercepts were calculated for greater than 58% Fe cut.
     A Scoping Study has commenced on the
    development of the Meletse Deposit, with the
    report due during the March Quarter 2011.
    CORPORATE
     The Company announced a 1 for 10 bonus
    issue in November.
     The Company issued 19,166,400 shares
    following the exercise of options during
    December.
     The Company?s Isaac Plains loan facility was
    fully repaid during the Quarter.
     Cash and liquid investments total approximately
    $288.2 million at the end of the Quarter.
     Additional staff employed during the Quarter to
    meet Aquila?s expansion requirements.
    MANGANESE
    Avontuur Manganese Project
     Diamond and RC drilling continued during the
    Quarter at the Gravenhage Manganese Deposit
    with significant (>40% Mn) intercepts including:
     1.9m at 47.2% Mn from 229m in GHEX006
     2.7m at 40.4% Mn from 122m in GHEX012
     1.5m at 45.9% Mn from 82m in GHEX155
     2.0m at 47.7% Mn from 83m and 2m at
    42.8% Mn from 87m in GHEX156
     3.5m at 42.8% Mn from 127m in GHEX164
     4.0m at 43.7% Mn from 94m in GHEX183
     4.0m at 43.8% Mn from 87m in GHEX184
     1.5m at 46.1% Mn from 93m in GHEX201
     1.53m at 41.2% Mn from 130m in GHEX202
     4.5m at 42.2% Mn from 70m in GHEX207
     2.6m at 40.2% Mn from 265.28m in
    GHEX209
     5.0m at 40.6% Mn from 99m and 3.5m at
    40.8% Mn from 108m in GHOP002
     4.1m at 43.3% Mn from 88m and 2.3m at
    42.6% Mn from 94m in GHOP004
     2.3m at 45.3% Mn from 65m and 2.1m at
    42.4% Mn from 69m in GHOP006
     An updated JORC Resource for the Gravenhage
    Manganese Deposit is due to be released early
    in 2011.
     The Feasibility Study for the development of the
    Gravenhage Deposit has commenced.
     An application for a Mining Right for the
    Avontuur Manganese Project has been
    submitted to the Department of Minerals and
    Resources in South Africa, along with a draft
    Social and Labour Plan.
    COAL
    AQA Quarterly Report ? December 2010 4
    ISAAC PLAINS COAL MINE
    (Aquila Resources Limited 50%)
    Isaac Plains Coal Mine is an operating open cut
    coal mine located east of Moranbah in the Bowen
    Basin in central Queensland. The coal products are
    a mix of metallurgical and thermal coals, which are
    exported through Dalrymple Bay Coal Terminal
    (DBCT).
    Production
    Isaac Plains? operational results during the Quarter
    were impacted heavily by adverse weather. During
    December, the area received 350mm of rainfall
    which exceeded the previous December record of
    318mm by 32mm and the average December
    rainfall of 97mm by 253mm.The rainfall principally
    came in two specific events which resulted in loss
    of access to the mine and flooding of the N1 pit and
    the CHPP. Force majeure was declared on the
    existing sales contracts due to the inability of the
    mine to process and deliver coal while recovery and
    repairs were undertaken.
    CHPP Flooding at Isaac Plains Coal Mine
    Major Project activities during the Quarter
     There were no Lost Time Injuries (LTIs) during
    the Quarter with the 12 month rolling average
    LTI Frequency Rate for the mine being
    maintained at zero LTIs per million man hours
    worked.
     A total of 5.9M bank cubic metres (bcm) of
    overburden was moved, which was below
    budget for the period. The main loss of
    production was recorded in December where
    movement was 75% below budget.
     A total of 394Kt of saleable coal was produced
    during the Quarter. Again this result was under
    budget mainly due to mining and CHPP
    downtime during December. The yield, however,
    averaged 84% which was an excellent result
    despite the volume reduction.
     The dragline construction lost minimal time due
    to the weather impact and remains on schedule
    to be completed and operational in the June
    Quarter 2011.
    Isaac Plains Coal Mine
    After rain has been dewatered and mined
    Table 1 ? Isaac Plains Coal Mine Production Results
    Calendar Quarter Financial YTD
    December
    2009
    September
    2010
    December
    2010 2010 2011
    Overburden BCM 5,431,898 9,558,413 5,917,493 11,948,372 15,475,906
    Mining Tonnes 571,157 933,441 422,709 1,587,286 1,356,150
    CHPP Feed Tonnes 796,210 938,670 466,485 1,678,740 1,405,155
    CHPP Product Tonnes 601,910 684,986 390,870 1,271,030 1,075,856
    Yield % 75.6% 73.0% 84.1% 75.7% 76.6%
    Railings Tonnes 751,959 643,569 453,165 1,513,911 1,096,734
    Shipping Tonnes 775,445 491,961 625,388 1,497,612 1,117,349
    COAL
    AQA Quarterly Report ? December 2010 5
    Table 2 ? Isaac Plains Coal Mine Sales Results (tonnes)
    Calendar Quarter Financial YTD
    December
    2009
    September
    2010
    December
    2010 2010 2011
    Coking Coal 177,576 74,053 106,382 413,084 180,435
    PCI 221,927 217,574 313,623 286,485 531,197
    Thermal Coal 375,942 200,334 205,383 798,043 405,717
    Total 775,445 491,961 625,388 1,497,612 1,117,349
    Coal Sales
     Isaac Plains Coal Mine recorded 625Kt of coal
    sales during the Quarter which was an excellent
    result considering the impact of the wet weather
    late in the Quarter. There were no sales in
    December with the mine declaring Force
    majeure due to the rain events. These sales will
    be delayed into 2011.
     The Company, through its 100% subsidiary IP
    Coal Pty Ltd, assumed marketing responsibility
    for its 50% share of product from the Isaac
    Plains mine from 15 November 2010. The first
    sale under the new arrangements has been
    completed with a shipment of 75Kt semi soft
    coking coal due for despatch during the March
    Quarter 2011.
    EAGLE DOWNS HARD COKING COAL
    PROJECT
    (Aquila Resources Limited 50%)
    Eagle Downs Hard Coking Coal Project is a
    proposed underground longwall coal mine located
    to the south of Moranbah in the Bowen Basin and
    immediately adjacent to and down dip of BHPB
    Mitsubishi Alliance?s Peak Downs Mine.
    A Definitive Feasibility Study (DFS) is currently
    being undertaken and, subject to securing
    appropriate rail and port capacity for the Project,
    completion is due in the June Quarter 2011.
    The Project schedule contemplates commencing
    construction in 2011 with longwall production
    commencing in 2014, initially at a rate of up to
    4.6Mtpa from a single longwall. The study includes
    an expansion case with the introduction of a second
    longwall to increase production to 8Mtpa from 2020.
    Major Project activities during the Quarter
     There were no Lost Term Injuries (LTIs) during
    the Quarter with the 12 month rolling average
    LTI Frequency Rate for the Eagle Downs Hard
    Coking Coal Project being maintained at zero
    LTIs per million man hours worked.
     The field work programme continued during the
    Quarter but was hampered by rainfall from
    November. The balance of the programme will
    be completed in the March Quarter 2011. Work
    completed during this Quarter included:
     The 2D seismic programme was completed
    and interpretation undertaken.
     Quality tests were completed on the first
    large diameter quality core.
     Geotechnical drilling on the shaft and drift
    sites was commenced.
     Work continued on the Definitive Feasibility
    Study (DFS).
     The design for the underground mine layout
    in all three target seams was finalised and
    scheduled.
     The technical reports for underground,
    surface infrastructure and CHPP design
    continued.
     Tender packages for all areas were
    completed and released. A number of these
    have already closed and are being evaluated.
     QR has commenced undertaking a review of
    the rail loop design.
     Approvals
     Eagle Downs Environmental Management
    Plan is being reviewed by the Department of
    Environment Resource Management (DERM)
    with the expectation that a draft
    Environmental Approval will be issued during
    the March Quarter 2011.
     Negotiations for landowner compensation
    agreements continued this Quarter.
     Logistics
     An expression of interest (EOI) was lodged
    for the Stage 2 expansion of the Wiggins
    Island Coal Terminal (WICT). This is
    presently scheduled to be available between
    2015 and 2016.
    COAL
    AQA Quarterly Report ? December 2010 6
     The Project remains in the queue for the next
    expansion of the Dalrymple Bay Coal
    Terminal (DBCT) which is not expected to be
    available before the end of calendar 2016 at
    the earliest.
     The Manager is preparing an EOI for
    capacity at the new expansion at Abbot Point
    Coal Terminal (APCT) which is expected to
    be available in 2016.
     The legal proceedings which were
    commenced by a subsidiary of the Company,
    following the decision by a subsidiary of Vale
    not to support the Abbot Point and GAPE
    offers of port and rail capacity, continued to
    be progressed towards a 2011 trial date.
    WASHPOOL HARD COKING COAL PROJECT
    (Aquila Resources Limited 100%)
    The Washpool Hard Coking Coal Project is located
    north west of Blackwater in the Bowen Basin. It is a
    proposed open cut hard coking coal mine.
    The Project schedule contemplates commencement
    of construction to follow the grant of the Mining
    Lease in mid 2012. Production is planned to
    commence early 2013 targeting annual production
    of 2.6Mtpa.
    A DFS is currently being undertaken and
    completion is due in the September Quarter 2011.
    The completed study will inform the development
    decision for the Project.
    Major Project Activities during the Quarter
    Definitive Feasibility Study Progress
     The exploration programme being undertaken
    for the DFS has been delayed due to the wet
    weather and is expected to commence during
    the March Quarter 2011.
     The studies for the DFS have been tendered
    and awarded and commenced during the
    Quarter.
     The surface infrastructure study is being
    undertaken by GHD.
     The CHPP study is being undertaken by DRA
    Pacific.
     The mining study is being undertaken by
    Xenith.
     Initial mining studies undertaken in the DFS
    indicated that the annual production from the
    mine should be increased from the 1.6Mtpa
    considered in the Feasibility Study to 2.6Mtpa
    due to favorable unit cost considerations. The
    Project is now targeting the revised output.
    Project Logistics
    The Washpool Project is one of the eight Stage 1
    Participants of the Wiggins Island Coal Terminal.
    During the Quarter, the WICET project progressed
    under the Capacity Commitment Deed (CCD)
    funding provided by the Participants. This funding
    has enabled WICET to appoint Worley Parsons as
    its PCM contractor and approach both the domestic
    and international financial markets. Significant
    contracts as required under the mandate that
    WICET has from the Queensland Government were
    concluded during the Quarter.
    The Stage 1 Participants were granted
    authorisation during the Quarter from the Australian
    Competition and Consumer Commission (ACCC) to
    collectively negotiate with QR for the construction of
    the required infrastructure to support the new coal
    terminal. This was to allow the parties to deal with
    the monopoly position that QR has over the rail
    infrastructure in Queensland. This situation was
    exacerbated during the Quarter when the
    Queensland Government privatised QR through a
    float on the Australian Stock Exchange. As
    negotiations have reached an impasse at the
    commercial level, this matter is now being brought
    to the Queensland Competition Authority (QCA).
    Negotiations for above rail services have continued
    with offers being evaluated during the Quarter.
    Approvals
    The Draft EIS was submitted to DERM on 23
    December, 2010. This commences the review
    period DERM has to review the EIS against the
    Terms of Reference prior to the document going out
    for public review which is expected during the
    March Quarter 2011.
    Onsite Groundwater Bore
    COAL
    AQA Quarterly Report ? December 2010 7
    TALWOOD COKING COAL PROJECT
    (Aquila Resources Limited 100%)
    The Talwood Coking Coal Project is a potential
    underground coking coal mine, which would target
    the Leichhardt and Vermont seams in the Rangal
    coal measures. The Project area is located northwest
    of Moranbah in the Bowen Basin and is
    located immediately adjacent to BHPB Mitsubishi
    Alliance?s Goonyella Riverside Hard Coking Coal
    Mine.
    Project Activities during the Quarter
    The exploration programme for the Project was
    completed during the Quarter.
    Work commenced on the Project Concept study
    report which is scheduled to be completed in the
    June Quarter 2011. This Study is reviewing mining
    options in the three seams which have mineable
    targets; the Leichhardt and Vermont Seams from
    the Rangal Coal Measures along with the thick
    Middle Goonyella seam from the Moranbah Coal
    Measures. The target seams, while continuous
    throughout the tenement have distinct mining
    domains, based on mining thickness and quality.
    The Leichhardt seam at its shallowest is at a depth
    of 50m and dips at about 1 in 10 throughout much
    of the tenement.
    Updated Resource Estimate
    The total Resource has increased significantly from
    83.4Mt (in April 2009) to 246.6Mt (Dec 2010). In
    addition there has been a significant improvement
    in JORC classification of the Resource status from
    23.8Mt Indicated and 59.6Mt Inferred to 137.1Mt
    Indicated and 109.4Mt Inferred.
    Recent work involved:
     The drilling of an additional 62 holes across the
    tenement, with 21 cored holes.
     Identification of mining domains from the target
    seams based on coal thickness and quality.
     Coal quality investigations which highlighted the
    various properties of the upper two seams.
     The addition of 21 cored bores, with both raw
    and clean coal results, have been processed
    since the previous Resource Statement was
    released.
     Four holes have drilled through the Moranbah
    Coal Measures and confirmed the continuation
    of a 5m+ thick Middle Goonyella seam.
    The outcomes of this work include:
     Total Resource of 246.5Mt.
     Indicated Resources have increased
    substantially to 137.1Mt.
     Tonnage results by seam are detailed in Table 3
    below .
     Clear and defined mining domains for the target
    seams.
     Yields for the Leichhardt seam peak at 78% for
    a combined Coking and Thermal product (F1.50
    @ 9.9% Ash) and average 63.6% (F1.50 @
    10.9% Ash).
     Yields for the Vermont seam peak at 65% for a
    combined Coking and Thermal product exbands
    (F1.50 @ 10.4% Ash) and average 48.5%
    (F1.50 @ 11.9% Ash).
    This has resulted in a significantly more detailed
    and robust geological model, with a clearer
    definition of the mining domains of the upper seams
    and a better understanding of seam thickness and
    coal quality.
    With future work it is expected that:
     Resource definition will continue to improve
    reported tonnages and increase confidence
    levels for the Leichhardt seam.
     Further exploration will see the Vermont seam
    improve its Resources status.
     Further holes will target the Goonyella seams
    and determine coal quality parameters.
    Following further exploration and completion of the
    mining studies, an assessment of Reserves will be
    undertaken with a view to development of an
    underground longwall mining operation.
    Table 3 ? Total In-Situ Coal Resource Statement ? Talwood Coking Coal Project
    Seam
    Measured
    Million Tonnes
    Mt
    Indicated
    Mt
    Total Measured
    and Indicated
    Mt
    Inferred
    Mt
    Total Measured
    Indicated &
    Inferred
    Mt
    Upper Leichhardt - 50.3 50.3 10.6 60.9
    Vermont1 - 68.3 68.3 32.5 100.8
    Middle Goonyella - 18.5 18.5 66.3 84.8
    Total - 137.1 137.1 109.4 246.5
    1. The Vermont Seam contains a tuff band, the tonnage of which has been omitted from the Resource Statement calculations.
    IRON ORE
    AQA Quarterly Report ? December 2010 8
    WEST PILBARA IRON ORE PROJECT
    (Aquila Resources Limited 50%)
    The West Pilbara Iron Ore Project is a proposed
    ?direct ship? iron ore operation, the first stage of
    which is expected to export 30Mtpa from a new
    multi-user port at Anketell Point.
    DEVELOPMENT
    Approvals
    Conditional approval was granted by the Joint
    Venture Participants to undertake mine
    development for Stage 1 of the West Pilbara Iron
    Ore Project.
    The Public Environmental Review (PER) document
    for the development of Anketell Port was released
    for a public review period that closes on
    28 February 2011. The PER provides for the
    environmental approval of a multi-user port, in
    addition to the specific port infrastructure
    requirements of the West Pilbara Iron Ore Project.
    The public review of the PER describing the mine
    and rail elements of the Project was completed
    during the Quarter and a full response to public
    submissions was submitted to the State Office of
    the Environmental Protection Authority (OEPA).
    The OEPA accepted the response and commenced
    assessment of the proposal, with a report of its
    assessment expected during the March Quarter
    2011.
    Environmental surveys to provide baseline data
    continued and a suite of management plans have
    been drafted. Applications for a number of
    secondary environmental approvals, to be
    submitted in 2011, were also progressed during the
    Quarter.
    Preparatory discussions have been undertaken with
    representative Native Title groups to commence
    formal Native Title negotiations in 2011.
    Mining and Processing
    A maiden JORC Ore Reserve Estimate for the
    Stage 1 development of 445Mt of Proven and
    Probable Reserves was reported during the Quarter
    and are detailed in Table 4 below. Product 2 is
    intended for sale at the end of the Project life, if it
    cannot be blended with suitable additional
    resources yet to be defined.
    Proven and Probable Reserves represent 74% of
    the total Stage 1 development Measured and
    Indicated Resource. New pit designs have resulted
    in a significantly lower overburden to ore ratio of
    1.13, previously 1.85, and a mine schedule for 15
    years based on a production of 30Mtpa.
    Product Development
    The phased sinter test work programme,
    investigating the potential to substitute West Pilbara
    Fines (WPF) in sinter feed, has been completed. A
    total of five test reports have been issued to all
    Memorandum of Understanding (MoU) signatories,
    with the sixth to be issued next Quarter, once the
    report is completed.
    Further consignments of WPF samples were
    delivered to potential customers in China, Japan
    and Korea for evaluation as part of the MoU
    process. Various mills that had previously received
    samples, have reported test work results.
    Project sponsored and independent mill testing
    have derived similar conclusions, that WPF can be
    substituted or added to most sinter blends at levels
    of up to 15%, with minimal impact on sinter
    productivity and sinter properties.
    An additional four MoU have been signed, resulting
    in 38 MoU now in place with leading steel mills in
    China, Japan, Korea and Taiwan. These MoU
    outline the process for independent and mutual test
    work, as well as evaluation of ore to determine the
    market position of the WPF product.
    This work, along with VIU analysis, will eventually
    be used to support steel mills in providing Letters of
    Intent to purchase ore once the project is in
    production.
    Table 4 ? Stage 1 Development Proved and Probable Reserves
    Product Category
    Tonnes
    Mt
    Fe
    %
    Al2O3
    %
    SiO2
    %
    P
    %
    LOI
    %
    Product 1
    Proven 145.2 58.40 3.29 4.87 0.08 7.77
    Probable 244.1 56.71 3.41 5.96 0.06 8.86
    Total 389.3 57.34 3.37 5.55 0.07 8.45
    Product 2
    Proven 20.5 55.09 3.96 6.81 0.09 9.58
    Probable 35.3 55.05 3.95 7.35 0.09 9.16
    Total 55.8 55.07 3.96 7.15 0.09 9.31
    TOTAL
    Proven 165.7 57.99 3.38 5.11 0.08 7.99
    Probable 279.4 56.50 3.48 6.13 0.06 8.90
    Total 445.1 57.05 3.44 5.75 0.07 8.56
    Waste 504.0
    IRON ORE
    AQA Quarterly Report ? December 2010 9
    Engineering
    Expressions of interests have been received, for the
    provision of Project Managing Contractor (PMC)
    services. In March Quarter 2011, a short list of
    companies will be generated and tenders for PMC
    services invited.
    Geotechnical investigations continued along the rail
    corridor. The second phase of offshore
    geotechnical drilling near Anketell Point
    commenced and will assist in detailed design and
    the development of a dredging contract.
    Expansion Projects
    The Hardey Project Pre-Feasibility Study (PFS)
    metallurgical work was completed during the period,
    along with initial ?sighter? sinter testing, the results of
    which proved positive. The PFS results are
    expected to be reported during the March Quarter
    2011.
    The proposed product from the Hardey Project is a
    100% direct ship fines product, which has sintering
    characteristics similar to Rio?s Pilbara Blend Fines
    (PBF) and BHPB?s Mt Newman Fines (MNF), at
    20% and 10% replacement respectively.
    EXPLORATION
    Golder & Associates Pty Ltd completed the remodelling
    of the West Pilbara Iron Ore Project
    channel iron deposits of Catho Well (including
    Catho Well North), Jewel, Cochrane, Cardo Bore
    East, Cardo Bore North, Upper Cane, Trinity Bore,
    Kens Bore and Kens Bore East.
    An updated Resource Statement was completed
    and released to the ASX during the Quarter. The
    updated Resource Statement is summarised in
    Table 5 and the location of the Deposits is shown in
    Figure 1.
    Exploration activity continued during the Quarter on
    the exploration drilling of channel and detrital iron
    targets. Work included:
     continuation of an RC drilling programme at the
    Weckl prospect;
     commencement of a drilling programme for
    beneficiation test work at the Weckl prospect;
     commencement of an RC drilling programme at
    the Downey prospect;
     commencement of an RC drilling programme at
    the Buckland Hills prospect;
     continuation of an infill RC drilling programme at
    the Hardey Deposit.
    Weckl
    The Weckl prospect is prospective for detrital style
    iron mineralisation. The main target consists of
    three valleys - West Weckl, East Weckl and Central
    Weckl. The three main channels drain to the north
    where they converge and flow out onto the
    relatively flat Weckl Plain.
    RC drilling continued at the Weckl prospect during
    the Quarter with 86 holes completed for 2,991m
    drilled.
    Table 5 ? Stage 1 Development Resource Statement
    JORC
    Classification Mt Fe
    %
    P
    %
    SiO2
    %
    Al2O3
    %
    S
    %
    Mn
    %
    MgO
    %
    LOI
    %
    Measured 209 57.8 0.079 5.29 3.56 0.013 0.029 0.082 7.95
    Indicated 392 56.2 0.065 6.30 3.69 0.018 0.038 0.113 8.94
    Inferred 86 55.4 0.061 6.85 3.86 0.019 0.049 0.136 9.38
    TOTAL 687 56.6 0.069 6.06 3.67 0.017 0.037 0.106 8.69
    IRON ORE
    AQA Quarterly Report ? December 2010 10
    Figure 1 ? Deposit and Prospect Locations
    Better results (intercepts >20m) received from the
    Weckl RC drilling included:
     24m @ 57.65% Fe, 2.22% Al2O3, 7.85% SiO2,
    0.13% P, 0.01% S, 6.68% LOI from 16m in
    WKRC092;
     20m @ 56.21% Fe, 2.64% Al2O3, 6.75% SiO2,
    0.11% P, 0.03% S, 9.63% LOI from 16m in
    WKRC140;
     20m @ 55.83% Fe, 1.47% Al2O3, 11.84% SiO2,
    0.1% P, 0.02% S, 6.38% LOI from 18m in
    WKRC141;
     24m @ 57.13% Fe, 3.38% Al2O3, 8.67% SiO2,
    0.1% P, 0.02% S, 5.13% LOI from 6m in
    WKRC206;
     22m @ 58.18% Fe, 2.5% Al2O3, 6.77% SiO2,
    0.12% P, 0.02% S, 6.72% LOI from 6m in
    WKRC214;
     30m @ 56.71% Fe, 3.33% Al2O3, 8.87% SiO2,
    0.09% P, 0.02% S, 5.97% LOI from 16m in
    WKRC218;
     22m @ 56.81% Fe, 2.47% Al2O3, 6.69% SiO2,
    0.12% P, 0.02% S, 8.46% LOI from 8m in
    WKRC270.
    All intercepts were calculated for greater than 52% Fe cut.
    The detrital mineralisation encountered varies in
    iron grade from <50 to 60% with relatively high
    silica and low to moderate alumina. Better quality
    mineralisation is located in the upper drainages.
    Validation of drill logs and production of first pass
    sectional interpretation has commenced in
    preparation for geological modelling and Resource
    estimation.
    Ten aircore drill holes for 291m were also
    completed during the Quarter, with the aim of
    collecting bulk composite samples for size fraction
    analysis. The analysis will allow conclusions to be
    drawn on the suitability of the detrital material for
    beneficiation. Results of the size fraction analyses
    are pending.
    Aboriginal heritage surveys for the continuation of
    100m X 100m infill drilling have commenced and
    are approximately 80% completed.
    Heritage surveying and infill drilling will continue at
    the Weckl prospect next Quarter.
    IRON ORE
    AQA Quarterly Report ? December 2010 11
    Table 6 ? Weckl Drill Hole Locations
    Prospect Hole ID Easting Northing From Intercept Al2O3
    %
    SiO2
    %
    P
    %
    S
    %
    LOl
    %
    Fe
    Cut
    %
    Weckl WKRC088 515806 7545217 28m 10m @ 54.00% Fe 6.27 13.36 0.030 0.010 2.25 52
    Weckl WKRC090 515403 7545205 24m 8m @ 52.80% Fe 6.13 14.80 0.030 0.010 2.55 52
    Weckl WKRC092 516204 7545604 16m 24m @ 57.65% Fe 2.22 7.85 0.130 0.010 6.68 52
    Weckl WKRC102 515800 7546003 24m 10m @ 57.86% Fe 1.72 9.72 0.090 0.030 5.20 52
    Weckl WKRC103 515598 7546003 22m 14m @ 55.89% Fe 1.53 13.06 0.100 0.010 4.84 52
    Weckl WKRC109 514402 7546406 18m 6m @ 56.87% Fe 3.10 9.38 0.080 0.010 3.52 52
    Weckl WKRC117 512998 7546728 4m 8m @ 52.80% Fe 6.59 13.30 0.040 0.020 3.05 52
    Weckl WKRC124 512998 7547196 26m 6m @ 54.50% Fe 3.34 8.58 0.050 0.010 9.75 52
    Weckl WKRC134 512409 7548000 8m 14m @ 55.19% Fe 2.38 11.77 0.060 0.030 6.18 52
    Weckl WKRC135 510607 7545609 30m 10m @ 55.86% Fe 1.23 13.27 0.090 0.020 4.88 52
    Weckl WKRC136 510798 7545595 18m 16m @ 56.22% Fe 1.33 11.59 0.160 0.020 6.08 52
    Weckl WKRC138 509999 7546396 14m 12m @ 56.20% Fe 5.16 10.83 0.040 0.010 2.52 52
    Weckl WKRC140 510402 7546379 16m 20m @ 56.21% Fe 2.64 6.75 0.110 0.030 9.63 52
    Weckl WKRC141 510596 7546376 18m 20m @ 55.83% Fe 1.47 11.84 0.100 0.020 6.38 52
    Weckl WKRC206 512907 7543990 6m 24m @ 57.13% Fe 3.38 8.67 0.100 0.020 5.13 52
    Weckl WKRC208 513107 7544423 14m 12m @ 53.67% Fe 3.77 12.68 0.070 0.040 5.59 52
    Weckl WKRC209 512920 7544797 24m 14m @ 54.03% Fe 4.98 11.53 0.060 0.020 5.11 52
    Weckl WKRC212 512893 7546000 14m 12m @ 54.68% Fe 5.21 12.55 0.050 0.010 2.56 52
    Weckl WKRC214 517007 7543560 6m 22m @ 58.18% Fe 2.50 6.77 0.120 0.020 6.72 52
    Weckl WKRC215 516797 7543584 14m 18m @ 56.98% Fe 2.94 5.98 0.140 0.020 8.85 52
    Weckl WKRC216 516611 7543594 4m 14m @ 55.36% Fe 2.88 8.61 0.120 0.020 8.35 52
    Weckl WKRC218 516190 7544012 16m 30m @ 56.71% Fe 3.33 8.87 0.090 0.020 5.97 52
    Weckl WKRC219 515992 7543995 12m 14m @ 58.23% Fe 3.39 9.58 0.040 0.020 2.78 52
    Weckl WKRC223 515881 7544405 18m 10m @ 53.82% Fe 4.70 15.68 0.040 0.010 1.82 52
    Weckl WKRC227 515287 7545214 24m 10m @ 53.14% Fe 4.00 10.92 0.090 0.020 8.22 52
    Weckl WKRC230 515888 7545218 8m 12m @ 52.33% Fe 5.68 15.95 0.030 0.010 2.54 52
    Weckl WKRC234 515510 7545596 30m 10m @ 55.48% Fe 4.59 11.92 0.050 0.010 3.06 52
    Weckl WKRC237 515690 7545995 24m 18m @ 55.53% Fe 1.69 12.98 0.120 0.010 5.23 52
    Weckl WKRC238 515490 7545998 20m 12m @ 53.32% Fe 2.52 11.34 0.110 0.020 9.01 52
    Weckl WKRC239 515414 7546000 18m 6m @ 53.67% Fe 4.37 11.36 0.080 0.030 5.67 52
    Weckl WKRC257 512894 7547141 10m 10m @ 55.64% Fe 4.60 6.87 0.060 0.040 7.23 52
    Weckl WKRC268 510703 7545615 16m 16m @ 57.64% Fe 0.76 10.87 0.110 0.030 5.48 52
    Weckl WKRC269 510899 7545597 18m 8m @ 52.95% Fe 1.59 14.92 0.110 0.020 7.15 52
    Weckl WKRC270 511078 7545950 8m 22m @ 56.81% Fe 2.47 6.69 0.120 0.020 8.46 52
    Weckl WKRC271 510907 7545988 20m 6m @ 54.17% Fe 1.26 13.47 0.120 0.010 7.19 52
    Weckl WKRC272 510703 7545985 20m 14m @ 56.82% Fe 1.39 10.43 0.100 0.020 6.32 52
    Weckl WKRC273 510690 7546393 10m 10m @ 57.28% Fe 2.83 6.52 0.080 0.030 7.42 52
    Weckl WKRC274 510520 7546399 28m 6m @ 58.58% Fe 1.32 6.70 0.140 0.020 7.65 52
    Weckl WKRC275 510294 7546381 10m 6m @ 56.40% Fe 3.75 8.78 0.060 0.040 5.76 52
    Weckl WKRC285 511092 7547217 12m 8m @ 54.75% Fe 4.62 12.22 0.060 0.020 3.40 52
    Weckl WKRC292 509689 7547596 18m 8m @ 53.48% Fe 6.68 12.84 0.050 0.010 2.64 52
    IRON ORE
    AQA Quarterly Report ? December 2010 12
    Figure 2 ? Weckl Drill Hole Locations
    Figure 3 ? Downey Drill Hole Locations
    IRON ORE
    AQA Quarterly Report ? December 2010 13
    Downey
    The Downey prospect is located north-west of
    Weckl at the confluence of several creek systems,
    where channels merge from the east, west and
    south of the Weckl plain. The majority of
    sedimentary input is likely to have been from the
    south, where the headwater creeks of the Weckl
    system are located approximately 10km away.
    The Downey drilling aimed to test two alternate
    styles of mineralisation:
     Reworked channel iron or detrital material
    originating from the Weckl area below the
    surface cover; and/or
     Remnant channel iron material present in an
    interpreted tributary of the Robe River, below the
    surface cover.
    During the Quarter, a total of 169 RC drill holes
    were completed for a total of 5,166m drilled. Better
    results (intercepts >15m) received from the RC
    drilling included:
     18m @ 54.88% Fe, 2.42% Al2O3, 7.49% SiO2,
    0.06% P, 0.01% S, 10.9% LOI from 10m in
    DORC016;
     18m @ 56.40% Fe, 3.91% Al2O3, 6.56% SiO2,
    0.11% P, 0.01% S, 8.05% LOI from 18m in
    DORC031;
     30m @ 54.29% Fe, 2.99% Al2O3, 8.29% SiO2,
    0.08% P, 0.01% S, 10.41% LOI from 4m in
    DORC053;
    All intercepts were calculated for greater than 52% Fe cut.
    A full set of intercepts (>5m) are reported in Table 7
    and Figure 3 shows the location of these drill holes.
    To the north, an outcropping channel iron formation
    is present. RC drilling indicates that it is
    approximately 30m thick and reaches a maximum
    thickness of 45m.
    To the south, east and west, RC drilling, preliminary
    drill hole validation and sectional interpretation have
    indicated a continuous, thin blanket of recent
    colluvial gravels and alluvial detritals up to 10m
    thick, covering a highly variable canga unit that is
    often strongly cemented by vitreous goethite.
    Additional infill drilling has been planned in the
    north, where better assay results have been
    returned.
    Table 7 ? Downey Intercepts
    Prospect Hole ID Easting Northing From Intercept Al2O3
    %
    SiO2
    %
    P
    %
    S
    %
    LOl
    %
    Fe
    Cut
    %
    Downey DORC006 510803 7557399 8m 10m @ 53.46% Fe 3.99 9.58 0.060 0.010 9.24 52
    Downey DORC007 510800 7557204 10m 6m @ 54.17% Fe 3.09 11.50 0.040 0.010 7.22 52
    Downey DORC013 509993 7557996 16m 12m @ 54.23% Fe 3.63 7.42 0.090 0.010 9.98 52
    Downey DORC015 509994 7557004 16m 10m @ 54.00% Fe 3.80 7.55 0.060 0.010 10.83 52
    Downey DORC016 510008 7556806 10m 18m @ 54.88% Fe 2.42 7.49 0.060 0.010 10.90 52
    Downey DORC023 509299 7557998 6m 10m @ 54.95% Fe 3.35 7.69 0.080 0.010 9.80 52
    Downey DORC031 507999 7559408 8m 6m @ 55.30% Fe 4.31 6.55 0.060 0.010 9.53 52
    Downey DORC031 507999 7559408 18m 18m @ 56.40% Fe 3.91 6.56 0.110 0.010 8.05 52
    Downey DORC034 508196 7559007 2m 8m @ 53.17% Fe 3.61 8.68 0.060 0.010 11.02 52
    Downey DORC034 508196 7559007 24m 8m @ 55.95% Fe 2.99 7.99 0.120 0.010 8.31 52
    Downey DORC035 508207 7558604 6m 8m @ 54.50% Fe 3.49 7.19 0.050 0.010 10.86 52
    Downey DORC036 508199 7558201 8m 6m @ 52.77% Fe 3.14 10.98 0.060 0.010 9.61 52
    Downey DORC047 508200 7556198 20m 10m @ 55.26% Fe 3.24 7.45 0.070 0.010 9.77 52
    Downey DORC050 508234 7557401 14m 6m @ 54.13% Fe 2.76 8.29 0.050 0.010 11.00 52
    Downey DORC051 508202 7557593 4m 8m @ 54.63% Fe 3.13 9.91 0.050 0.020 7.96 52
    Downey DORC052 508203 7557792 4m 14m @ 55.99% Fe 2.41 8.38 0.060 0.010 8.50 52
    Downey DORC053 508198 7558001 4m 30m @ 54.29% Fe 2.99 8.29 0.080 0.010 10.41 52
    Downey DORC058 507808 7555600 14m 6m @ 55.37% Fe 2.54 9.02 0.040 0.020 8.70 52
    Downey DORC069 508003 7557401 10m 8m @ 55.35% Fe 2.81 7.72 0.060 0.010 9.76 52
    Downey DORC073 507396 7556208 12m 6m @ 52.23% Fe 2.45 11.20 0.050 0.020 10.77 52
    IRON ORE
    AQA Quarterly Report ? December 2010 14
    Buckland Hills
    During the Quarter a temporary exploration camp
    was established at the Buckland Hills prospect.
    Heritage surveys were completed and a first pass
    RC drilling programme commenced. A total of 117
    RC drill holes for 8,474m were drilled in the
    Quarter. See Figure 4 for the drill hole locations.
    The Buckland Hills prospect area is located within a
    tributary of the Bungaroo Creek and the drilling
    targeted a buried CID body constrained by the
    morphology of the present-day drainage. Better
    drill hole intersections indicate up to 184m of
    mineralised CID in the centre of the channel under
    approximately 35m of alluvial cover. Initial drilling
    indicates a U-shaped channel between 500 and
    700m wide within which are layers of CID units with
    variable clay and pisoid content. The assessment
    of the current drilling is ongoing and assays results
    from the centre of the channel are pending.
    Hardey
    Continued exploration effort has focussed on infill
    drilling to increase the understanding of the bedded
    iron mineralisation at the Hardey deposit. A total of
    72 RC drill holes for 11,386m were drilled in the
    Quarter (Figure 5). The infill drilling programme has
    been planned to refine the ore envelopes and
    improve geological understanding. Better results
    (intercepts >80m) received from the infill RC drilling
    programme include:
     90m @ 59.58% Fe, 3.59% Al2O3, 5.04% SiO2,
    0.129% P, 0.005% S, 5.55% LOI from surface in
    HARC287;
     138m @ 63.12% Fe, 1.6% Al2O3, 3.02% SiO2,
    0.142% P, 0.004% S, 4.4% LOI from surface in
    HARC329;
     128m @ 60.89% Fe, 2.76% Al2O3, 4.64% SiO2,
    0.153% P, 0.006% S, 4.8% LOI from surface in
    HARC351;
     84m @ 62.54% Fe, 1.32% Al2O3, 3.99% SiO2,
    0.122% P, 0.002% S, 4.81% LOI from 64m in
    HARC356;
     106m @ 62.58% Fe, 1.95% Al2O3, 2.62% SiO2,
    0.178% P, 0.001% S, 5.2% LOI from 10m in
    HARC361;
     108m @ 62.31% Fe, 2.42% Al2O3, 3.12% SiO2,
    0.14% P, 0.004% S, 4.74% LOI from 26m in
    HARC366.
    All intercepts were calculated for greater than 58% Fe cut.
    A full set of intercepts (>40m) are reported in Table
    8 and Figure 5 shows the location of these drill
    holes.
    Sectional and drill hole validation has commenced
    in preparation for remodelling of the Hardey
    deposit. Preliminary mineralisation envelopes have
    been created in preparation for revision of the
    Resource Statement.
    Figure 4 ? Buckland Hill Drill Hole Locations
    IRON ORE
    AQA Quarterly Report ? December 2010 15
    Figure 5 ? Hardey Drill Hole Locations
    Table 8 ? Hardey Intercepts
    Prospect Hole ID Easting Northing From Intercept Al2O3
    %
    SiO2
    %
    P
    %
    S
    %
    LOl
    %
    Fe
    Cut
    %
    Hardey HARC276 529999 7462253 4m 62m @ 62.60% Fe 1.91 3.85 0.096 0.000 4.22 58
    Hardey HARC277 530000 7462349 8m 40m @ 62.06% Fe 2.22 4.00 0.125 0.001 4.47 58
    Hardey HARC278 529999 7462299 16m 42m @ 58.57% Fe 3.51 6.15 0.123 0.001 6.01 58
    Hardey HARC279 529999 7462401 12m 40m @ 61.64% Fe 1.83 5.24 0.109 0.003 4.12 58
    Hardey HARC282 529797 7462401 2m 58m @ 64.06% Fe 1.32 3.12 0.094 0.002 3.48 58
    Hardey HARC284 529801 7462501 0m 42m @ 60.40% Fe 2.50 5.00 0.130 0.011 5.58 58
    Hardey HARC285 529798 7462452 6m 56m @ 59.28% Fe 3.71 5.95 0.104 0.003 5.02 58
    Hardey HARC287 529702 7462527 0m 90m @ 59.58% Fe 3.59 5.04 0.129 0.005 5.55 58
    Hardey HARC288 529703 7462556 14m 62m @ 61.10% Fe 2.86 3.91 0.144 0.003 5.23 58
    Hardey HARC289 529654 7462508 0m 66m @ 62.48% Fe 1.41 2.85 0.119 0.002 5.92 58
    Hardey HARC290 529705 7462484 16m 66m @ 60.38% Fe 2.87 5.14 0.146 0.003 5.05 58
    Hardey HARC293 529894 7462362 2m 52m @ 61.10% Fe 1.99 4.77 0.142 0.006 5.36 58
    Hardey HARC296 529694 7462432 30m 66m @ 64.18% Fe 1.40 1.96 0.136 0.003 4.47 58
    Hardey HARC297 529608 7462511 2m 50m @ 58.53% Fe 3.76 6.04 0.139 0.005 5.99 58
    Hardey HARC310 529497 7462249 0m 42m @ 60.93% Fe 3.05 4.34 0.132 0.024 4.77 58
    Hardey HARC317 530047 7462299 12m 42m @ 59.56% Fe 2.77 5.14 0.176 0.005 5.81 58
    Hardey HARC318 529716 7462350 76m 46m @ 61.34% Fe 1.87 5.14 0.158 0.002 4.82 58
    Hardey HARC321 529801 7462280 74m 58m @ 62.64% Fe 0.76 4.66 0.115 0.002 4.53 58
    Hardey HARC328 530049 7461849 0m 68m @ 61.82% Fe 1.87 2.80 0.151 0.004 6.08 58
    Hardey HARC329 530100 7461856 0m 138m @ 63.12% Fe 1.60 3.02 0.142 0.004 4.40 58
    Hardey HARC330 529997 7461763 2m 66m @ 63.42% Fe 2.21 2.32 0.146 0.005 4.01 58
    Hardey HARC331 530017 7461792 0m 64m @ 63.46% Fe 1.59 2.57 0.133 0.007 4.33 58
    Hardey HARC332 529996 7461849 50m 50m @ 59.69% Fe 3.50 4.41 0.161 0.003 5.85 58
    Hardey HARC333 529949 7461835 2m 44m @ 61.60% Fe 2.91 3.26 0.129 0.003 5.12 58
    IRON ORE
    AQA Quarterly Report ? December 2010 16
    Prospect Hole ID Easting Northing From Intercept Al2O3
    %
    SiO2
    %
    P
    %
    S
    %
    LOl
    %
    Fe
    Cut
    %
    Hardey HARC335 529936 7461883 36m 78m @ 63.22% Fe 1.34 2.01 0.136 0.003 5.66 58
    Hardey HARC336 530202 7461949 32m 50m @ 62.20% Fe 1.77 3.40 0.142 0.002 5.28 58
    Hardey HARC337 530244 7461986 48m 52m @ 63.18% Fe 1.35 2.23 0.146 0.002 5.38 58
    Hardey HARC338 530246 7461999 26m 60m @ 61.35% Fe 1.53 4.03 0.134 0.006 6.11 58
    Hardey HARC351 530260 7461781 0m 128m @ 60.89% Fe 2.76 4.64 0.153 0.006 4.80 58
    Hardey HARC352 530348 7461766 18m 70m @ 63.37% Fe 1.86 2.48 0.158 0.002 4.43 58
    Hardey HARC353 530155 7461747 6m 70m @ 63.29% Fe 1.84 1.76 0.161 0.006 5.15 58
    Hardey HARC354 530045 7461797 16m 54m @ 63.87% Fe 1.97 2.71 0.118 0.002 3.48 58
    Hardey HARC355 530158 7461898 40m 52m @ 63.42% Fe 1.62 2.27 0.151 0.002 4.77 58
    Hardey HARC356 530162 7461906 64m 84m @ 62.54% Fe 1.32 3.99 0.122 0.002 4.81 58
    Hardey HARC357 530496 7461830 2m 62m @ 60.92% Fe 2.38 3.60 0.194 0.003 6.04 58
    Hardey HARC359 530451 7461897 14m 76m @ 62.24% Fe 1.79 4.71 0.141 0.002 3.89 58
    Hardey HARC360 530507 7461940 4m 50m @ 63.17% Fe 1.16 1.99 0.139 0.010 5.77 58
    Hardey HARC361 530350 7461887 10m 106m @ 62.58% Fe 1.95 2.62 0.178 0.001 5.20 58
    Hardey HARC362 530299 7461879 46m 42m @ 62.65% Fe 2.25 2.30 0.194 0.003 5.08 58
    Hardey HARC363 530244 7461866 32m 58m @ 62.41% Fe 2.29 2.20 0.189 0.004 5.47 58
    Hardey HARC364 530036 7461697 44m 58m @ 60.13% Fe 3.03 4.49 0.169 0.023 5.56 58
    Hardey HARC365 529998 7461597 22m 72m @ 61.83% Fe 2.43 2.55 0.185 0.009 5.83 58
    Hardey HARC366 529900 7461690 26m 108m @ 62.31% Fe 2.42 3.12 0.140 0.004 4.74 58
    Hardey HARC367 529805 7461690 52m 60m @ 61.42% Fe 3.39 4.29 0.107 0.004 3.94 58
    Hardey HARC368 529751 7461705 40m 44m @ 61.95% Fe 2.90 3.63 0.111 0.007 4.28 58
    Hardey HARC372 529705 7461803 18m 54m @ 62.17% Fe 2.14 2.53 0.141 0.013 5.79 58
    Hardey HARC374 529800 7461876 94m 60m @ 61.66% Fe 2.54 3.65 0.140 0.000 4.98 58
    Hardey HARC375 529808 7461999 70m 50m @ 62.12% Fe 2.16 3.41 0.144 0.002 4.90 58
    Hardey HARC377 529721 7462023 72m 44m @ 60.46% Fe 2.11 5.51 0.133 0.001 5.16 58
    Hardey HARC378 529474 7462080 60m 50m @ 62.86% Fe 2.25 2.59 0.153 0.001 4.74 58
    Hardey HARC379 529479 7462096 2m 60m @ 60.85% Fe 3.82 3.99 0.167 0.001 4.53 58
    Hardey HARC382 529598 7462073 78m 46m @ 63.44% Fe 1.97 2.60 0.155 0.002 3.97 58
    Hardey HARC383 529645 7462050 38m 42m @ 63.32% Fe 1.66 2.82 0.116 0.002 4.20 58
    Hardey HARC385 529804 7461746 0m 50m @ 62.40% Fe 1.98 2.72 0.137 0.017 5.41 58
    SOUTH AFRICA
    THABAZIMBI IRON ORE PROJECT
    (Aquila Resources Limited 74%)
    Exploration
    An updated JORC Resource Statement for the
    Meletse Deposit was released during the Quarter.
    Golder Associates Africa (Pty) Ltd was
    commissioned to construct a geological model and
    update the in-situ Resource Statement. The
    updated Resource of 47.6Mt at 62.9% Fe
    represents a 117% increase on the earlier
    Resource with approximately 33% of the updated
    Resource now in the Indicated category.
    The Meletse Iron Ore Deposit Resource Statement
    is shown in Table 9 and the iron ore lodes that
    make up the Deposit are shown in Figure 6.
    The Deposit is composed of several irregular
    shaped, hard, lumpy high grade (+60% Fe) iron ore
    lodes, outcropping along a lateral extent in excess
    of 600m. The iron ore lodes dip approximately 400
    to the southwest near the outcrop and flatten to less
    than 200 at the dip extent of the lodes. The iron ore
    lodes bifurcate and coalesce in profile and are
    gently folded along strike.
    The lumpy hard ores consist mainly of martitehematite
    assemblages and the basal and upper
    contacts with the proto Banded Iron Formation are
    gradational. The high grade hematite is suitable for
    open pit mining of direct shipping ore (DSO) for
    domestic and/or international customers.
    IRON ORE
    AQA Quarterly Report ? December 2010 17
    During the Quarter, 11 RC drill holes were
    completed for 3,127m with significant high-grade Fe
    intercepts reported in Table 10. Figure 7 shows the
    location of the drill holes completed during the
    Quarter and the geology of the Meletse Iron Ore
    Deposit area.
    An extensive RC drilling programme continues at
    the Deposit, which remains open along strike to the
    north and at depth to the west. A second track
    mounted RC drill rig is being mobilised to site in
    February and a diamond drill rig is scheduled for
    mid 2011.
    New tracks have been constructed both down dip
    and to the north of the Deposit, where greater
    thicknesses of iron ore and higher grades have
    been intercepted in recent drilling.
    The ongoing drilling will continue to test the strike
    and dip extent of the Deposit to increase both the
    size of the current Resource and to upgrade the
    JORC categories of the Resource.
    An upgraded Resource Statement is expected in
    the September Quarter-2011.
    Geotechnical and metallurgical diamond core
    drilling will provide data for consideration of a
    decision to commence a feasibility study in mid-
    2011.
    Figure 8 shows the area of the current Deposit
    Resource and the exploration target area to be drill
    tested.
    Table 9 ? Meletse Iron Ore Deposit Resource Statement
    MELETSE IRON ORE RESOURCE
    Resource
    Classifications
    Tonnes
    Mt
    Fe
    %
    SiO2
    %
    Al2O3
    %
    P
    %
    S
    %
    MnO
    %
    MgO
    %
    LOI
    %
    Indicated 15.9 63.6 6.22 1.07 0.031 0.045 0.783 0.076 1.00
    Inferred 31.7 62.5 8.89 0.82 0.044 0.041 1.078 0.054 1.19
    Total 47.6 62.9 8.00 0.91 0.040 0.043 0.979 0.061 1.13
    Figure 6 ? Meletse Iron Ore Lodes
    IRON ORE
    AQA Quarterly Report ? December 2010 18
    Table 10 ? Meletse Iron Ore Deposit Intercepts (>3m)
    Projection GCS Hartbeesheok 94 (Lo27), Declination -90o, Reverse Circulation Drill Holes Below detection limit.
    Hole ID Easting Northing From Intercept Al2O3 SiO2 P K2O LOl
    % % % % %
    DT38 -66810.09 2719649.76 254m 4m @ 61.56% Fe 1.63 9.46 0.02 0.01 0.95
    DT38 -66810.09 2719649.76 288m 3m @ 62.06% Fe 2.27 5.05 0.01 0.08 2.60
    DT40 -66698.84 2719298.82 200m 14m @ 64.55% Fe 0.75 5.58 0.01 0.10 0.63
    DT55 -66380.37 2719462.94 306m 3m @ 60.22% Fe 1.24 9.91 0.03 0.24 1.12
    DT50 -66701.64 2719296.86 148m 4m @ 60.45% Fe 0.50 9.57 0.03 0.10 2.72
    DT50 -66701.64 2719296.86 159m 8m @ 60.02% Fe 0.45 10.19 0.03 0.10 2.34
    DT50 -66701.64 2719296.86 182m 23m @ 66.14% Fe 0.19 3.22 0.02 0.11 0.41
    DT50 -66701.64 2719296.86 246m 11m @ 61.22% Fe 0.72 7.39 0.04 0.13 1.08
    DT56 -66426.93 2719354.69 273m 6m @ 55.19% Fe 0.59 2.66 0.08 0.53 3.01
    DT53 -66360.18 2719336.08 248m 27m @ 62.83% Fe 0.36 7.69 0.02 0.10 0.41
    DT60 -66552.73 2719555.54 210m 33m @ 65.75% Fe 0.61 4.06 0.06 0.14 0.74
    DT62 -66613.03 2719644.93 182m 6m @ 62.36% Fe 0.88 8.12 0.07 0.16 1.16
    DT62 -66613.03 2719644.93 202m 7m @ 62.31% Fe 0.49 10.46 0.04 0.10 0.89
    DT62 -66613.03 2719644.93 230m 31m @ 67.49% Fe 0.58 1.36 0.08 0.12 0.42
    DT65 -66605.75 2719271.48 232m 13m @ 65.43% Fe 0.24 4.61 0.02 0.10 0.37
    DT67 -66481.24 2719281.94 245m 5m @ 61.43% Fe 1.42 3.82 0.06 0.22 1.99
    Figure 7 ? Meletse Iron Ore Deposit Geology and Location of Drill Holes
    IRON ORE
    AQA Quarterly Report ? December 2010 19
    Figure 8 ? Meletse Iron Ore Deposit Lodes, Resource extent and Exploration Target Area
    Development
    A Scoping Study has commenced on the
    development of the Meletse Deposit. The study will
    consider the possible mining options, as well as the
    provision of utilities such as power and water, and
    will include a comprehensive geotechnical study by
    Golder & Associates.
    A meeting was held with Transnet Freight Rail
    (TFR) to consider the transport of iron ore from the
    Meletse Deposit to the east coast for export to
    Asian markets. TFR has agreed to review the
    earlier studies into this proposal, in the context of
    more recent plans for the development of
    infrastructure for this region, with a new proposal to
    be submitted for the Company?s consideration.
    The Scoping Study is due for completion during the
    March Quarter 2011, and subject to its findings, a
    Feasibility Study is planned to commence during
    the June Quarter 2011 with a completion date
    scheduled during the June Quarter 2012.
    MANGANESE
    AQA Quarterly Report ? December 2010 20
    SOUTH AFRICA
    AVONTUUR MANGANESE PROJECT
    (Aquila Resources Limited 74%)
    Exploration
    The Gravenhage Manganese Deposit is situated at
    the northern end of the Company?s Avontuur
    tenement, which is located approximately 30km
    north of the Kalahari Manganese Field, South
    Africa?s premier manganese producing area (see
    Figure 9).
    Drilling continued at the Gravenhage Deposit, with
    39 drill holes completed or in progress at Quarter?s
    end for 4,786m (diamond, RC and percussion precollar).
    Significant intercepts are reported in Table
    11 and are shown in Figure 10.
    A programme of geotechnical diamond core drilling
    (GHOP) and large diameter (LD) metallurgical
    diamond core drilling also commenced during the
    Quarter. High grade assays were received from the
    geotechnical core drilling in the shallow area of the
    Deposit with grades ranging from 42.3% Mn to
    53.5% Mn over intervals ranging from 1.5m to
    4.05m. The results of this drilling has confirmed and
    enhanced the Resource model and supports the
    mining of high grade manganese in an initial open
    pit development
    Exploration drilling on the Gravenhage Deposit
    concluded during the Quarter, with an updated
    Manganese Resource due to be released during
    the March Quarter 2011. This updated Resource
    Statement will form the basis for the proposed
    Feasibility Study.
    Figure 9 ? Location of Gravenhage and Eersbegint Manganese Deposits
    MANGANESE
    AQA Quarterly Report ? December 2010 21
    Table 11 ? Gravenhage Manganese Deposit Intercepts
    Hole
    Number Easting (X) Northing (Y) From (m) Interval
    (m)
    Mn
    %
    Fe
    %
    SiO2
    %
    Al2O3
    %
    CaO
    %
    P2O5
    %
    LOI
    %
    GHEX006* 679001.26 7034821.76 229 1.9 47.20 6.00 4.63 0.23 7.48 0.05 11.27
    GHEX012 679628.79 7034945.61 122 2.7 40.38 8.48 6.93 0.25 10.01 0.05 11.14
    GHEX028 681003.65 7034822.27 136 5.5 36.49 12.04 9.29 0.32 6.53 0.09 9.39
    GHEX103 679820.47 7034186.60 238 4.5 38.09 11.29 8.64 0.19 9.93 0.00 8.00
    GHEX155 680510.31 7035227.76 82 1.5 45.87 15.57 2.21 0.43 0.57 0.08 9.91
    GHEX156 680848.83 7035258.94
    83 2.0 47.70 12.09 1.95 0.42 0.42 0.055 12.81
    87 2.0 42.75 8.42 2.89 0.30 7.89 0.085 15.96
    GHEX164 679545.49 7035020.06 127 3.5 42.84 21.95 2.83 0.32 2.62 0.16 1.91
    GHEX169 679224.56 7033372.53 338 4.1 37.28 10.56 9.41 0.18 9.15 0.02 8.49
    GHEX171 679805.27 7033447.50 297 1.6 39.76 12.72 10.98 0.25 2.29 0.02 6.08
    GHEX175 678081.85 7033305.27 461 2.0 37.03 9.40 13.38 0.54 6.13 0.06 7.80
    GHEX180 680851.62 7035183.20 98 1.5 35.33 12.17 16.93 1.25 0.88 0.10 10.89
    GHEX181 680718.59 7035039.95 66 1.5 37.20 17.10 12.70 0.39 0.41 0.05 8.73
    GHEX183 681282.49 7035067.42 94 4.0 43.71 8.88 9.14 0.29 6.82 0.06 8.92
    GHEX184 681576.99 7034797.95 87 4.0 43.81 12.88 8.78 0.28 3.65 0.07 5.66
    GHEX185 681448.72 7034650.06 107 3.5 38.06 12.53 8.61 0.32 8.21 0.06 7.79
    GHEX186 682015.48 7034680.76 74 4.0 36.66 10.82 18.59 0.25 0.55 0.08 10.61
    GHEX187 682164.34 7034552.34 104 4.5 38.58 11.78 9.10 0.28 7.85 0.06 9.58
    GHEX188 682178.27 7034266.46 113 4.0 36.06 11.12 9.12 0.26 13.31 0.06 9.48
    GHEX189 682044.12 7034100.09 123 5.5 39.21 10.78 8.71 0.28 10.69 0.06 8.70
    GHEX190 681775.68 7033814.34 148 3.5 35.10 11.91 10.00 0.28 11.27 0.06 10.09
    GHEX191 682472.80 7033996.51 83 1.5 39.03 9.74 19.29 0.23 0.95 0.07 8.32
    GHEX192 682784.55 7033443.59 69 1.5 37.63 10.75 4.08 0.25 8.84 0.08 15.99
    GHEX193 680785.80 7033912.12 134 1.3 34.13 11.24 17.93 0.33 3.80 0.07 6.78
    GHEX195 681344.47 7033936.27 197 3.1 35.51 11.59 10.83 0.39 8.61 0.06 9.57
    GHEX197 681637.63 7033664.67 166 3.5 35.64 12.40 10.62 0.49 7.41 0.07 8.95
    GHEX198 681373.77 7033364.56 199 3.0 37.82 12.41 10.72 0.31 8.16 0.07 6.84
    GHEX200 680720.18 7034887.42 82 2.5 38.54 20.46 2.04 0.52 2.96 0.08 10.26
    GHEX201 681432.06 7034935.45 93 1.5 46.10 8.58 9.77 0.31 1.42 0.67 9.60
    GHEX202 680186.79 7034442.16 130 1.5 41.17 13.43 13.02 0.43 0.15 0.08 4.75
    GHEX203 681653.27 7034876.67
    74 1.5 37.79 10.25 13.03 0.26 1.55 0.01 10.57
    77 3.0 40.60 10.33 4.57 0.21 3.48 0.02 6.53
    GHEX205 682245.71 7034339.40 100 3.5 38.40 12.16 9.66 0.22 10.75 0.02 6.50
    GHEX206 682539.11 7034071.96
    70 1.5 34.94 5.64 6.44 0.12 8.56 0.03 17.94
    73 1.5 49.97 11.34 13.53 0.15 1.20 0.00 10.48
    GHEX207 680941.74 7035289.77 70 4.5 42.18 11.10 4.90 0.22 1.83 0.03 11.00
    GHEX209 679376.44 7034464.41 265 2.6 44.79 8.62 6.82 0.17 6.45 0.00 6.65
    GHEX210 679303.92 7034659.36 180 3.0 37.70 13.50 13.10 0.40 8.28 0.07 4.79
    GHOP002** 679998.74 7035039.08
    99 5.0 40.63 15.52 2.92 0.31 2.72 0.11 12.16
    108 3.5 40.76 10.99 8.36 0.37 8.17 0.07 8.54
    GHOP004** 679898.70 7035138.16
    88 4.0 43.26 15.59 6.53 0.34 3.60 0.11 6.57
    94 2.3 42.56 10.42 6.84 0.36 4.14 0.08 11.31
    GHOP006** 679799.63 7035238.19
    65 2.3 45.26 13.34 4.66 0.32 0.37 0.09 10.23
    69 2.1 42.43 16.55 4.86 0.27 0.46 0.13 9.65
    Projection (WGS84 S34), Declination -90o, Diamond Drill Holes. * Resampled drill hole. ** Geotechnical diamond core drilling -700 /0000.
    MANGANESE
    AQA Quarterly Report ? December 2010 22
    Figure 10 ? Location of Drill Holes with significant manganese intercepts
    Exploration drilling is due to recommence during the
    March Quarter on targets south of the Gravenhage
    Deposit. Drilling late in the Quarter at Haakdoorn
    intersected upper and lower manganese bodies,
    separated by a mafic sill, similar to the
    mineralisation style at Gravenhage.
    Historical drilling at Haakdoorn intersected high
    grade manganese and the area is a priority target
    for structurally related hydrothermal upgrade of
    manganese mineralisation.
    Programmes of ground gravity and magnetics have
    been completed and were interpreted during the
    Quarter.
    RC and diamond drilling is scheduled for early in
    2011, with four target areas identified and shown in
    Figure 11.
     Target A: To find a shallow lower manganese
    body, which has been upgraded at
    the basin edge by meteoric water
    flows leaching out carbonates from
    the manganese ore;
     Target B: To find shallow upper manganese
    bodies that have been upgraded and
    preserved due to structural changes
    in the shape of the basin;
     Target C: To find upper manganese bodies at
    shallow depths that have been
    preserved and upgraded due to
    interpreted localised thrust
    structures;
     Target D: Strike and dip extensions of the
    upper and lower manganese bodies
    that have been recently drilled at
    Haakdoorn.
    MANGANESE
    AQA Quarterly Report ? December 2010 23
    Figure 11 ? Location of Exploration Drill Targets within the Avontuur Basin
    Development
    An application for a Mining Right for the Avontuur
    Manganese Project was submitted to the
    Department of Minerals and Resources in South
    Africa during the Quarter, along with a draft Social
    and Labour Plan. Confirmation that the application
    complies with the requirements of the relevant Act
    has been received from the Department.
    Preparatory work for the Feasibility Study for the
    development of the Gravenhage Deposit has
    advanced during the period.
    Geotechnical drilling was completed, with laboratory
    results awaited before the final report can issue. A
    large diameter drilling programme has been
    initiated for the collection of sample for metallurgical
    testing of the ore. Transnet Freight Rail officials inspecting large diameter core at
    Gravenhage
    MANGANESE
    AQA Quarterly Report ? December 2010 24
    Geotechnical Drilling at Gravenhage
    Golder & Associates has revised the geological
    model, incorporating the recent drilling results.
    Once the model is completed, VBKOM Consulting
    Mining Engineers will conduct the Mine Design
    Study for the development of the Gravenhage
    Deposit.
    JLT Mining Services has been selected to conduct
    the detailed engineering and infrastructure design
    for this development.
    Synergistics has completed an Environmental
    Scoping Report and baseline studies for the
    completion of an Environmental Impact
    Assessment. The Environmental Scoping Study will
    be submitted to the Department of Minerals and
    Resources during the March Quarter 2011, in
    support of the Mining Right application submitted
    during the last Quarter.
    As a member of the Ore Line Expansion Project
    team, investigating the expansion of the Northern
    Cape to Saldanha Bay export corridor, the
    Company has been considering an FEL1 level
    study of the various options for that expansion. The
    Steering Committee for that Project will be
    considering the outcomes of that study and any
    future work during the March Quarter 2011.
    Engineering studies for the Avontuur Manganese
    Project will commence during the March Quarter
    2011 with the Feasibility Study scheduled for
    completion during the September Quarter 2011.
    Subject to all necessary approvals, construction
    could commence early in 2012. Subject to the
    availability of rail and port capacity, first ore railed is
    scheduled during the June Quarter 2013.
    CORPORATE
    AQA Quarterly Report ? December 2010 25
    BONUS ISSUE
    The Company announced at the Annual General
    Meeting that there would be a 1 for 10 bonus issue
    to recognise the significant progress that the
    Company had made in its coal, iron ore and
    manganese projects over the previous 12 months
    and with a view to encouraging greater liquidity in
    the Company?s shares (which in turn should
    improve the likelihood of the Company being
    included in the S&P/ASX100 Index).
    EXERCISE OF OPTIONS
    During the course of December 5,000,000 options
    were exercised in respect of 19,166,400 shares
    and a total of $20m was received by the Company.
    STAFF
    During the Quarter Aquila and its joint ventures
    increased staff significantly, including a number of
    senior personnel, to meet the demands of the
    Company?s expanding operations.
    BELVEDERE DISPOSAL
    The legal proceedings which were commenced by
    a subsidiary of Vale and which have delayed
    determination of a Fair Market Value for the sale of
    the Company?s 24.5% interest in the Belvedere
    Hard Coking Coal Project, progressed towards a
    2011 trial date.
    CASH RESERVES AND LIQUID INVESTMENTS
    Cash reserves and liquid investments total
    approximately $288.2 million at the end of the
    Quarter.
    The Company?s Isaac Plains loan facility was fully
    repaid during the Quarter.
    For further information please contact:
    Mr Tony Poli
    Executive Chairman
    Telephone: (08) 9423 0111
    Facsimile: (08) 9423 0133
    Email: [email protected]
    Visit us at: www.aquilaresources.com.au
    COMPETENCY STATEMENTS
    AQA Quarterly Report ? December 2010 26
    Talwood Coking Coal Project
    The information in this announcement that relates to the Resource Statement has been based on information compiled by Mr Rod
    Doyle. He is a full-time employee of Aquila Resources Limited and holds shares in the Company. He is a qualified Geologist (BSc
    Geology UOW 1978 and MAppSc UNSW 1988) with some 30 years? experience in coal geology, coal mining and resource evaluation.
    He is a member of the Australasian Institute of Mining and Metallurgy and qualifies as a Competent Person under the JORC Code. Mr
    Doyle consents to the inclusion of this information in this statement and related announcements as well as presentations, where the
    information presented is in the form and context in which it appears.
    West Pilbara Iron Ore Project
    The information in this report that relates to exploration results is based on information compiled by Mr Stuart Tuckey, who is a Member
    of The Australasian Institute of Mining and Metallurgy and is a full-time employee of API Management Pty Ltd. Mr Tuckey has sufficient
    experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is
    undertaking to qualify as a Competent Person as defined in the 2004 Edition of the ?Australasian Code for Reporting of Exploration
    Results, Mineral Resources and Ore Reserves?. Mr Stuart Tuckey consents to the inclusion in the report of the matters based on the
    information in the form and context in which it appears.
    The information in this report that relates to the Catho Well Catho Well North, Cardo Bore East, Cardo Bore North, Cochrane, Jewel,
    Kens Bore, Kens Bore East, Trinity Bore and Upper Cane Mineral Resources was prepared under the supervision of Mr Stuart Tuckey
    and Mr Richard Gaze who are members of the Australasian Institute of Mining and Metallurgy. Mr Tuckey is full-time employee of the
    API Management Pty Ltd. Mr Gaze is a full-time employee of Golder Associates Pty Ltd. Mr Tuckey and Mr Gaze have sufficient
    experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are
    undertaking to qualify as Competent Persons as defined in the 2004 Edition of the ?Australasian Code of Reporting of Exploration
    Results, Mineral Resources and Ore Reserves?. Messrs Tuckey and Gaze consent to the inclusion in the report of the matters based on
    the information in the form and context which it appears.
    The information in this report that relates to Ore Reserves is based on information compiled by Mr Steve Craig, Managing Director of
    ORElogy (Mining Consultants). Mr Craig is a Member of the Australasian Institute of Mining and Metallurgy and has sufficient
    experience which is relevant to the style of mineralisation and type of deposit under consideration, and to the activity he is undertaking,
    to qualify as a Competent Person as defined in the 2004 Edition of the ?Australasian Code for Reporting of Exploration Results, Mineral
    Resources and Ore Reserves?. Mr Craig consents to the inclusion in the report of the matters based on the information in the form and
    context in which it appears.
    Thabazimbi Iron Ore Project
    The estimates of iron ore Resources for the Meletse Iron Ore Deposit presented in this report have been prepared in accordance with
    the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves 2004 (?the JORC Code?).
    The estimates are based on information compiled by Mr Brent E Green who is a member of the Australian Institute of Geoscientists and
    a full time employee of the Company. Mr Green has sufficient experience which is relevant to the style of mineralisation and type of
    deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the JORC Code.
    Mr Green consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
    The information in this report, insofar as it relates to Mineral Exploration activities, is based on information compiled by Mr Brent E
    Green who is a member of the Australian Institute of Geoscientists, and who has more than five years experience in the field of activity
    being reported on. Mr Green is a full-time employee of the Company. Mr Green has sufficient experience which is relevant to the style
    of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person
    as defined in the 2004 Edition of the ?Australasian Code of Reporting of Exploration Results, Mineral Resources and Ore Reserves?. Mr
    Green consents to the inclusion in the report of the matters based on his information, in the form and context in which it appears.
    Avontuur Manganese Project
    The information in this report, insofar as it relates to Mineral Exploration activities, is based on information compiled by Mr Brent E
    Green who is a member of the Australian Institute of Geoscientists, and who has more than five years experience in the field of activity
    being reported on. Mr Green is a full-time employee of the Company. Mr Green has sufficient experience which is relevant to the style
    of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person
    as defined in the 2004 Edition of the ?Australasian Code of Reporting of Exploration Results, Mineral Resources and Ore Reserves?. Mr
    Green consents to the inclusion in the report of the matters based on the information in the form and context in which it appears.
    Appendix 5B
    Mining exploration entity quarterly report
    + See chapter 19 for defined terms.
    Appendix 5B Page 1
    Rule 5.3
    Appendix 5B
    Mining exploration entity quarterly report
    Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10.
    Name of entity
    AQUILA RESOURCES LIMITED
    ABN Quarter ended (?current quarter?)
    81 092 002 769 DECEMBER 2010
    Consolidated statement of cash flows
    Cash flows related to operating activities
    Current quarter
    $A?000
    Year to date
    (6 months)
    $A?000
    1.1 Receipts from product sales and related
    debtors
    60,934 98,838
    1.2 Payments for (a) exploration & evaluation
    (b) development
    (c) production
    (d) administration
    (23,743)
    (4,626)
    (31,571)
    (3,763)
    (44,315)
    (7,249)
    (61,334)
    (6,785)
    1.3 Dividends received - -
    1.4 Interest and other items of a similar nature
    received
    3,373 8,790
    1.5 Interest and other costs of finance paid (450) (645)
    1.6 Income taxes paid - -
    1.7 Other (Service charges) 109 344
    Net Operating Cash Flows 263 (12,356)
    Cash flows related to investing activities
    1.8 Payment for purchases of:
    (a) prospects
    (b) equity investments
    (c) other fixed assets
    (2,987)
    -
    (4,181)
    (2,987)
    (4,042)
    (4,874)
    1.9 Proceeds from sale of:
    (a) prospects
    (b) equity investments
    (c) other fixed assets
    -
    32
    -
    -
    37
    -
    1.10 Loans to other entities - -
    1.11 Loans repaid by other entities - -
    1.12 Other (Security deposits lodged) (20,488) (23,140)
    Net investing cash flows (27,624) (35,006)
    1.13 Total operating and investing cash flows
    (carried forward)
    (27,361) (47,362)
    Appendix 5B
    Mining exploration entity quarterly report
    + See chapter 19 for defined terms.
    Appendix 5B Page 2
    1.13 Total operating and investing cash flows
    (brought forward)
    (27,361) (47,362)
    Cash flows related to financing activities
    1.14 Proceeds from issues of shares, options,
    etc.
    20,000 22,074
    1.15 Proceeds from sale of forfeited shares - -
    1.16 Proceeds from borrowings - -
    1.17 Repayment of borrowings (5,215) (5,524)
    1.18 Dividends paid - -
    1.19 Other (provide details if material) - -
    Net financing cash flows 14,785 16,550
    Net increase (decrease) in cash held (12,576) (30,812)
    1.20 Cash at beginning of quarter/year to date 263,045 281,174
    1.21 Exchange rate adjustments to item 1.20 (226) (119)
    1.22 Cash at end of quarter 250,243 250,243
    Payments to directors of the entity and associates of the directors
    Payments to related entities of the entity and associates of the
    related entities
    Current quarter
    $A'000
    1.23 Aggregate amount of payments to the parties included in item 1.2 223
    1.24 Aggregate amount of loans to the parties included in item 1.10 -
    1.25 Explanation necessary for an understanding of the transactions
    Management Fees, Directors? Fees
    Non-cash financing and investing activities
    2.1 Details of financing and investing transactions which have had a material effect on
    consolidated assets and liabilities but did not involve cash flows
    2.2 Details of outlays made by other entities to establish or increase their share in projects in
    which the reporting entity has an interest
    Appendix 5B
    Mining exploration entity quarterly report
    + See chapter 19 for defined terms.
    Appendix 5B Page 3
    Financing facilities available
    Add notes as necessary for an understanding of the position.
    Amount available
    $A?000
    Amount used
    $A?000
    3.1 Loan facilities -1 -
    3.2 Credit standby arrangements - -
    1 ? The Company?s Isaac Plains cash advance and financial guarantee facility was repaid during the quarter.
    Estimated cash outflows for next quarter
    $A?000
    4.1 Exploration and evaluation 35,000
    4.2 Development 12,000
    4.3 Production 25,000
    4.4 Administration 3,000
    Total 75,0001
    1 ? Represents specified cash outflows only. Does not include cash inflows such as sales receipts and interest income.
    Reconciliation of cash
    Reconciliation of cash at the end of the quarter
    (as shown in the consolidated statement of cash
    flows) to the related items in the accounts is as
    follows.
    Current quarter
    $A?000
    Previous quarter
    $A?000
    5.1 Cash on hand and at bank 55,235 48,037
    5.2 Deposits at call 195,008 215,008
    5.3 Bank overdraft - -
    5.4 Other (provide details) - -
    Total: cash at end of quarter (item 1.22) 250,243 263,045
    Changes in interests in mining tenements
    Tenement
    reference
    Nature of interest
    (note (2))
    Interest at
    beginning
    of quarter
    Interest
    at end
    of
    quarter
    6.1 Interests in mining
    tenements
    relinquished, reduced
    or lapsed
    Appendix 5B
    Mining exploration entity quarterly report
    + See chapter 19 for defined terms.
    Appendix 5B Page 4
    6.2 Interests in mining
    tenements acquired or
    increased
    E47/2205
    Iron-ore ? Western Australia
    Granted 50% 50%
    Issued and quoted securities at end of current quarter
    Description includes rate of interest and any redemption or conversion rights together with prices and
    dates.
    Total number Number
    quoted
    Issue price per
    security (see
    note 3) (cents)
    Amount paid up per
    security (see note
    3) (cents)
    7.1 Preference
    +securities
    (description)
    7.2 Changes during
    quarter
    (a) Increases through
    issues
    (b) Decreases through
    returns of capital, buybacks,
    redemptions
    7.3 +Ordinary securities 374,314,049 374,314,049
    7.4 Changes during
    quarter
    (a) Increases through
    issues
    (b) Decreases
    through returns of
    capital, buy-backs
    19,166,400
    32,285,463
    19,166,400
    32,285,463
    $4.00 - See Note 7
    $Nil ? See Note 8
    $4.00 - See Note 7
    $Nil ? See Note 8
    7.5 +Convertible debt
    securities
    (description)
    7.6 Changes during
    quarter
    (a) Increases through
    issues
    (b) Decreases
    through securities
    matured, converted
    7.7 Options (description
    and conversion factor)
    4,590,000 -
    Exercise price
    See note 6.
    Expiry date
    See note 6.
    7.8 Issued during quarter
    7.9 Exercised during
    quarter 5,000,000 - $4.00 31 December 2010
    7.10 Expired during quarter
    7.11 Debentures
    (totals only)
    7.12 Unsecured notes
    (totals only)
    + S
    C
    1
    2
    Si
    Pr
    N
    1
    2
    3
    4
    5
    6
    7
    8
    See chapter 19
    Complia
    This
    with
    stan
    This
    gn here:
    rint name:
    Notes
    The q
    have
    want
    attac
    The ?
    minin
    invol
    its pe
    intere
    Issue
    items
    The d
    AASB
    Acco
    Stan
    stand
    Secu
    5,000
    ordin
    32,28
    share
    9 for defined te
    ance sta
    s statement
    accounting
    ndards acce
    s statement
    ______
    Directo
    Tony P
    quarterly repo
    e been finance
    ting to disclos
    ched to this re
    Nature of int
    ng tenements
    ved in a joint
    ercentage inte
    est and cond
    ed and quot
    s 7.1 and 7.3
    definitions in,
    B 1026: State
    ounting Stan
    dards for fore
    dard on that t
    urities issued
    Number Iss
    2,940
    1,650
    0,000 options
    nary shares a
    85,463 share
    e for every te
    erms.
    atement
    has been p
    g standards
    eptable to A
    does give a
    ___________
    or
    Poli
    ort provides a
    ed for the pas
    se additional i
    eport.
    terest? (items
    s acquired, ex
    venture agre
    erest in a min
    itions precede
    ed securities
    for fully paid
    , and provisio
    ement of Cas
    ndards ASX w
    eign entities.
    topic (if any) m
    but not quoted
    sued Ty
    0,000 Opt
    0,000 Opt
    s were exercis
    s a result of t
    es were issue
    en shares held
    Min
    t
    prepared un
    as defined
    ASX (see no
    true and f
    Da
    _______
    basis for inf
    st quarter and
    information is
    6.1 and 6.2)
    xercised or la
    eement and th
    ning tenemen
    ent in the list
    s The issue
    securities.
    ons of, AASB
    sh Flows appl
    will accept, fo
    If the standa
    must be com
    d as at 31 De
    ype
    tions
    tions
    sed during th
    the entitlemen
    ed pursuant
    d.
    ning explor
    nder accoun
    in the Corp
    ote 4).
    fair view of t
    ate: 31 Janu
    forming the m
    d the effect o
    s encouraged
    includes opti
    apsed during t
    here are cond
    nt, it should di
    required for
    price and am
    1022: Accou
    y to this repo
    or example, th
    ards used do
    plied with.
    ecember 2010
    Expiry D
    22 June
    1 July
    he quarter tha
    nt of the hold
    to a bonus i
    ration enti
    nting policie
    porations Ac
    the matters
    ary 2011
    market how the
    n its cash pos
    to do so, in a
    ons in respec
    the reporting
    ditions preced
    sclose the ch
    items 6.1 and
    ount paid up
    unting for Extr
    ort.
    he use of Inte
    not address a
    0.
    Date E
    2013
    2014
    at converted to
    er to bonus is
    ssue, at no
    App
    ity quarterl
    Append
    es which com
    ct or other
    s disclosed.
    e entity?s acti
    sition. An en
    note or note
    ct of interests
    period. If the
    dent which wi
    hange of perc
    d 6.2.
    is not require
    ractive Indust
    ernational Acc
    topic, the A
    Exercise Pric
    $7.6
    $11.4
    o 19,166,400
    ssues.
    consideration
    endix 5B
    ly report
    ix 5B Page 5
    mply
    ivities
    tity
    es
    s in
    e entity is
    ill change
    centage
    ed in
    tries and
    counting
    ustralian
    e
    5
    0
    0
    n, for one
 
watchlist Created with Sketch. Add AQA (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.