k8 do not hold you breath.
SRK have heaps of ground to cover before 2011 H1. Remember this mine was (according to SRK) have the first coal shipped out in June 2010 !
Few things srk need to resolve:
(1) permits & clearances for haulroad to port. I have not seen publicly available info to suggest they have completed this
(2) construct the haulroad itself to port. best estimates are 9-12 months construction. Couldn;t see anywhere in the report that they have started the road or something to that effect
(3) to develop the mine the need all permits in place. Some they have, some they haven't. How long is a piece of string for this one considering they are dealing with authorities who are know to take their time and rightly so.
(4) develop the mine - technically it is in a very difficult terrace & high rainfall area. There is a big river that runs smack bang in the middle of the North & East concessions. There are restrictions on loads on the river as well.
SRK need to be more realistic in their assessments. Having said that they could be very close to having the project started in 2011 H1, ie make more ground than now.
Good luck
- Forums
- ASX - By Stock
- SRK
- Ann: Investor Presentation
Ann: Investor Presentation , page-50
-
- There are more pages in this discussion • 4 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SRK (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.1¢ |
Change
0.001(3.33%) |
Mkt cap ! $9.931M |
Open | High | Low | Value | Volume |
3.1¢ | 3.4¢ | 3.1¢ | $675 | 21.25K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 83978 | 3.1¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.3¢ | 76808 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 12987 | 0.077 |
1 | 50000 | 0.075 |
1 | 250000 | 0.072 |
1 | 100000 | 0.071 |
1 | 50000 | 0.070 |
Price($) | Vol. | No. |
---|---|---|
0.080 | 19545 | 1 |
0.083 | 1300 | 1 |
0.084 | 90000 | 1 |
0.086 | 47000 | 1 |
0.088 | 10000 | 1 |
Last trade - 15.58pm 15/11/2024 (20 minute delay) ? |
Featured News
SRK (ASX) Chart |
The Watchlist
ACW
ACTINOGEN MEDICAL LIMITED
Will Souter, CFO
Will Souter
CFO
Previous Video
Next Video
SPONSORED BY The Market Online