    This DOE reference to EWC Pagbilao power plant isprobably what Cusi had in mind when referring to DoE having incorporated EWC inits plans re: operational power plants.

    18 March 2019 DOE publication:PrivateSector Initiated Power Projects as of 28 February 2019

    https://www.doe.gov.ph/electric-power/private-sector-initiated-power-projects-28-february-2019

    I just copied the reference to EWC pagbilao power plant

    FEASIBILIY STUDY:

    • Completed

    'ARRANGEMENT FOR SECURING THE REQUIRED LAND:

    Land isalready secured with a long lease entered into since 2007

    MARKETING OF GENERATING CAPACITIES:

    No specificoff taker yet but already have a discussion with Federation of PhilippineIndustries, intended to supply power into the Wholesale Electricity Spot Marketbut is also open to discussing

    potential off take arrangements as well

    • 100% WESM

    PERMITS AND OTHER REGULATORY REQUIREMENTS:

    • GIS for 300MW issued by NGCP on 8 August 2013 and revised on 3 July2013 for 600MW

    • Issued DOE Endorsement for Revised Capacity on 3 July 2013;

    • Revised DOE clearance for GIS submitted to NGCP on January 2014

    • GIS from NGCP for the 600MW was released on August 2014;

    • Several Resolutions has been issued on May 2014 (SangguniangBarangay Resolution, Sangguniang Bayan Resolution and Sangguniang PanlalawiganResolution) interposing no objection for

    the construction of a 600 MW Liquified Natural Gas (LNG) Power Plant;

    • On‐going processing of ECC for power plant

    FINANCING ARRANGEMENTS:

    • Financial Arrangement Secured

    • Syndicated Loan

    • Project Cost:$300M

    • Signing of loan agreement last 18 Sep 2015

    CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT:

    • Enteredinto a Sale and Purchase Agreement last October 2012 with Siemens Energy fortwo 200 MW gas turbines and the first 200MW turbine is expected to arrive bySeptember 2014

    • LNG Tank is currently at 50% construction completed as of August2014;

    COMMENCEMENT OF CONSTRUCTION:

    • December 2013

    • Completed

    Target testing and commissioning: March 2019

    Target commercialoperation: June 2019

 
watchlist Created with Sketch. Add EWC (ASX) to my watchlist
(20min delay)
Last
2.0¢
Change
-0.003(13.0%)
Mkt cap ! $29.24M
Open High Low Value Volume
2.1¢ 2.1¢ 1.9¢ $15.13K 757.5K

Buyers (Bids)

No. Vol. Price($)
2 1258505 1.8¢
 

Sellers (Offers)

Price($) Vol. No.
2.1¢ 77196 1
View Market Depth
Last trade - 15.59pm 29/11/2024 (20 minute delay) ?
EWC (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.