Near-term schedule
The next steps for Galena’s Abra project include:
- Completing the pre-feasibility study in September 2018;
- Additional infill drilling to convert more inferred resource material to the higher confidence indicated classification in late 2018; and
- Completing the marketing exercise with potential buyers, including smelters and traders, to obtain contract terms for Abra’s lead concentrate.
-