    Proposed TD: Depth : 3740mMD; (Vertical Well)
    Elevation:
    Ground Level is 57.2mAMSL
    Rotary Table is 62.9mAMSL
    Spud Date: 17:00 hrs, WST 22nd January 2008
    Present Depth at 0600 hrs: 3254m MD
    Time of Reporting: 0600 hrs, WST 3rd April 2008
    Operations Since Last
    Report: Drilled 216mm (8 ½”) hole from 2935m to 3254m MD.
    Current Operations: Circulating to condition and stabilise hole at 3254m.
    Hydrocarbon indications: Elevated mud gas readings were noted over a gross interval from
    2854 to 2983 metres.
    Comments:
    The well has encountered the primary objective Tournasian aged
    gas sands some 400 metres updip from the intersection of the
    same sands in the Yulleroo 1 well.
    The sands appear similar to those encountered in Yulleroo 1 with
    approximately 40 metres of potential gas pay. Wireline logs,
    pressure data and production test data are required to evaluate
    the reservoir potential of these sands.
    The forward plan is to drill ahead to the interpreted secondary
    objectives of the Laurel Limestones and the Famennian aged
    carbonate interval which is age equivalent to the reefal limestone
    section encountered in Stokes Bay 1. This operation is expected
    to take another 7 days, however hole conditions are causing
    some concern and a decision on the running of a liner to protect
    the section encountered to date and ensure the ability to drill to
    the deeper objectives will be taken as operational conditions
    require.
 