    Hi germainst,
    reading your comment about the 6 week wait time, I went back and examined GTE's drill program record.
    It took a while to build, could be errors or omissions in it, hope not.   One reason we (GTE) wait so long for Assay results
    could be:  time of year or because we're a very small co ?

    GTE  DRILLING  REVIEW  OCT  2017  -  JUNE  2018
    Management Action  Plans, Promises, Subsequent Events / Results
    YANDAL  WEST  May Queen (gold)  and  YERRIDA  SOUTH  Chisel  (copper)


    Column 1 Column 2 Column 3
    0 ASX  announcement
    Month  and Year
    YANDAL  WEST  (gold)  May Queen site
    YERRIDA  SOUTH  Chisel  (copper)
    1 OCTOBER
    19------------------

    21-------------------

    24------------------


    31-------------------


    19 Drill Program  announced
    PHASE  I  [  0  days]

    21 RC drill mobilized to site
    [2  days ]

    24 Drilling commences  at Yandal.  To take 3 weeks, 2 weeks turnaround. [0 days ]

    31 Yandal drilling program  begun  [7 days ]


    19 ------NIL

    21 ------NIL

    24 ------NIL


    31 --Chisel Gravity Survey Program begins  (Newexco )

    2 NOVEMBER
    9-----------------


    15----------------

    28----------------


    30---------------




    9 Yandal PHASE I  22 holes drilled  2297m [ 16 days]  Assays in 2-3 weeks.  Drilling to restart in early December



    28 Yandal ASSAY  RESULTS [ in 2 weeks 5 days]. PHASE  2Starts  next  week.


    30 NOV  28  results  RE-RELEASED


    RC  DRILL  RIG  USE
    2297M
    PHASE  I  OCT  21/  Nov  28 38  days  TO  COMPLETE


    9 ---------NIL



    15 Chisel Gravity Survey completed
    [  16 days ]

    28 ---------NIL



    30 ---------NIL


    3 DECEMBER
    4--------------------

    8---------------------

    16-------------------

    22------------------




    4 $2M of funds raised for Yandal Gold

    8 Yandal West PHASE  II  3000m planned  [ 0 days]

    16 GTE  General Meeting

    22 Yandal West PHASE  II
    1852m  RC  drilling done
    [ 14 days ]
    Assay results  in  Mid  January.
    More  drilling late  January

    RC  DRILL  RIG  USE
    4149M



    4 ---------NIL

    8 ---------NIL


    16 GTE  General Meeting


    22 ---------NIL



    4 JANUARY
    30-----------------


    31-----------------




    30 Yandal  ASSAY  RESULTS
    [ 15  days  later  than planned ]

    31  Q4  2017 Activities Report
    Q4  2017 Financial Report
    2097m  of drilling done.  A further 1200m  of drilling planned  AS  WEATHER PERMITS
    [ NO  drilling late January]

    RC  DRILL  RIG  USE
    4394M




    30 ---------NIL



    31  Q4  2017 Activities Report
    Q4  2017 Financial Report
    Chisel  drill planning has  begun






    5 FEBRUARY
    14-----------------





    14  No drilling at Yandal West  due to WET  weather


    RC  DRILL  RIG  USE
    4394M



    ---------NIL






    6 MARCH
    13--------------------





    15-----------------




    13  Yandal West  PHASE  II  1200m left  in  3000m program.  Now planning a further 1500m, then Diamond drilling after OTV survey
    ACTUAL  MAR  DRILLING
    1647m  (ASX May 14)


    15  Half  Yearly Report

    RC  DRILL  RIG  USE
    6041M




    13 ---------NIL






    15 ---------NIL
    Half  Yearly Report




    7 APRIL
    4---------------------


    18--------------------



    27-------------------


    30-------------------




    4 ---------NIL  Awaiting Assays


    18 ---------NIL Awaiting Assays


    27 ---------NIL Awaiting Assays



    30 ---------NIL Awaiting Assays
    Q1  2018 Activities Report
    Q1  2018 Financial Report





    4- Chisel drill target  identified.  1200m RC drilling planned, in conjunction with Newexco.

    18 -Chisel drilling commenced.  1000m
    (5x 200m deep holes)



    27 - 3  holes  drilled  (600m)
    RC  DRILL  breaks  down  .  MAJOR OVERHAUL REQUIRED.  Back in action in June.




    30 -Q1  2018 Activities Report
    Q1  2018 Financial Report

    RC  DRILL  RIG  USE
    6641M BREAKS  DOWN
    [  COULD  IT  HAVE  BEEN  CHECKED  & OVERHAULED  IN  FEB  ?  ]  [Possible outback field crew  vs  Perth planning crew  issue here ? ]

    8 MAY
    3-------------------



    10-----------------

    14------------------



    3 ---------NIL Awaiting Assays
    SANDFIRE  to  aerially examine Yerrida  North

    10 Investor Presentation



    14 Yandal West  PHASE  II  1647m DONE.  A  futher  1500m planned [  PHASE  II  Part  3 ? ]

    RC  DRILL  RIG  USE
    0M [ NIL  being repaired ]


    3 ---------NIL




    10 Investor Presentation




    14 ---------NIL




    9 JUNE
    19----------------




    19  Yandal West  2,316m RC drilled  - 26  holes.  SO  MORE  THAN  the  initial  1500m ABOVE.

    ASSAYS  IN  6  weeks.
    [  NOTES  {1} March ASSAYS  weren’t released until  mid –May , thus between 6 (mid March at best to 8 weeks at worse scenario).  {2} It could take so long, due to QUEUING  of various WA mining co’s wanting results, and  GTE  being so small a co !

    RC  DRILL  RIG  USE
    2316m


    19  ---------NIL
    NOTE  ASX  APR  30  company mentioned the choice of  EITHER Chisel or Yandal, once the RC drill was back in operation

    NOTE:  could GTE  drag back the RC drill back to Chisel in the intervening 6 weeks wait ?  NOT MENTIONED  in June 19th announcement. A shareholder could call the  co.  ????


    10
    THE  END​






    Comments welcomed.

    Cheers  Bluequartz
 
watchlist Created with Sketch. Add GTE (ASX) to my watchlist
(20min delay)
Last
2.8¢
Change
0.000(0.00%)
Mkt cap ! $14.35M
Open High Low Value Volume
2.8¢ 2.9¢ 2.8¢ $13.07K 465.9K

Buyers (Bids)

No. Vol. Price($)
1 186243 2.7¢
 

Sellers (Offers)

Price($) Vol. No.
3.0¢ 19948 1
View Market Depth
Last trade - 15.57pm 15/11/2024 (20 minute delay) ?
GTE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.