The Tyler County, TX well is ready for a workover rig to move in and complete the well.
Operator left enough boards on location for a workover rig to set on. Water tanks were also left on location in anticipation of a completion attempt in the near future.
To complete, the operator will do the following:
1. Move in workover rig with blow out preventer, power swivel, mud tank and pump.
2. Move in pipe racks and tubing
3. Open well and drill out cement to total depth
4. Run Cement Bond Log
5. Run Correlation Log to determine perforation depth
6. Perforate zone(s) Operator may utilize casing guns or perforate thru tubing
7. Treat well??
8. Replace blow out preventer with wellhead
9. Test well
10, Install flowlines & meters