Hi Oregyuy,
I can understand why you are referring to the directors as "pathalogical liars".
The following dates are from the Annual Reports from 2010 thru 2014.
2010 AR. First production of LNG from Sengkang will be First qtr 2012
2011 AR. First 1MTPA production of LNG will now likely occur from second qtr 2013.
2012 AR. Construction complete by the end of the first qtr 2014 and then commissioning begins for the first train.
2013 AR. Construction complete by the end of the second qtr 2014 and then commissioning begins.
2014 AR. Complete construction and commissioning and commence operations within this financial year ending 30th June 2015.
2015 AR. Anyone like to have a guess ????????? more, more undeliverable promises??
Not too sure what game they are playing and why?? but they need to come forward with honest dates very soon re Sengkang and Philippines Power Plant. There has to be an end date, and your date of .....eventually does not suit my pocket.
Palmtree
- Forums
- ASX - By Stock
- EWC
- Ann: Update on Major Projects
Ann: Update on Major Projects, page-19
-
- There are more pages in this discussion • 9 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Add EWC (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.0¢ |
Change
-0.003(13.0%) |
Mkt cap ! $29.24M |
Open | High | Low | Value | Volume |
2.1¢ | 2.1¢ | 1.9¢ | $15.13K | 757.5K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 1258505 | 1.8¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
2.1¢ | 77196 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 97 | 0.095 |
3 | 311964 | 0.094 |
1 | 300000 | 0.093 |
1 | 25000 | 0.092 |
3 | 54000 | 0.090 |
Price($) | Vol. | No. |
---|---|---|
0.096 | 20355 | 1 |
0.097 | 3101 | 1 |
0.099 | 60000 | 1 |
0.100 | 71326 | 2 |
0.105 | 220678 | 4 |
Last trade - 15.59pm 29/11/2024 (20 minute delay) ? |
EWC (ASX) Chart |