GRK 0.00% 0.2¢ green rock energy limited

Quality location?, page-26

  1. 5,732 Posts.
    This is part of ann mande 29/7/14
    WORK PROGRAMME.au

    4 month due diligence period

    Initial work programme commenced 25th July 2014 – mapping, rockchip sampling and trenching

    Initial Objectives:
    Investigate the potential widths and strike length of the Epanko North Prospect

    Identify potential TGC grade range and properties of mineralisation at Epanko NorthProspect

    Verify drill hole locations previously drilled at the Ndololo Prospect

    Systematically map, sample and trench the graphite schist units to determine thickness and strike potential at Ndololo Prospect

    Identification and preparation of key areas for resource drilling

    Onsite works expected to be completed in August 2014 – anticipate announcement of results in
    September 2014.
 
watchlist Created with Sketch. Add GRK (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.